10335 S CLOVIS AVE 90002

Certificate Information: 10335 S CLOVIS AVE 90002

Application / Permit
24014-10000-05432
Plan Check / Job No.
B24LA35460
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING TO ADD BATHROOM, ENLARGE BEDROOM, AND EXTEND KITCHEN.
Permit Issued
Issued on 12/20/2024
Issuing Office
Metro
Current Status
CofO Issued on 6/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2024 APPLICANT
Assigned to Plan Check Engineer 12/10/2024 CARLOS MONTES
Corrections Issued 12/10/2024 CARLOS MONTES
Plan Check Approved 12/20/2024 SAMUEL GONZALEZ
Issued 12/20/2024 APPLICANT
CofO in Progress 6/3/2026 ANSON MAGLASANG
Permit Finaled 6/3/2026 ANSON MAGLASANG
CofO Issued 6/3/2026 ANSON MAGLASANG
Permit Finaled 6/3/2026 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/18/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/19/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/16/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 6/16/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 6/16/2025 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 6/18/2025 Approved ANTHONY EGSON
Reinforced Concrete Frame 6/24/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 7/8/2025 Corrections Issued ANTHONY EGSON
Wood Frame 7/8/2025 No Access for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 7/17/2025 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Approved JOHN KLARIN
Insulation 7/17/2025 Partial Inspection JOHN KLARIN
ELECTRICAL-Rough 8/14/2025 Approved ANTHONY EGSON
HVAC-Rough 8/14/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 8/14/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 8/14/2025 Approved ANTHONY EGSON
Drywall Nailing 9/15/2025 Partial Approval ANTHONY EGSON
Insulation 9/15/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/15/2025 Partial Approval ANTHONY EGSON
Drywall Nailing 9/26/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/26/2025 Partial Inspection ANTHONY EGSON
Wood Frame 11/12/2025 Approved ANTHONY EGSON
Drywall Nailing 12/29/2025 Approved ARTHUR NEGRETE
HVAC-Rough 12/29/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 12/29/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 5/28/2026 Approved ARTHUR NEGRETE
Final 5/28/2026 OK to Issue CofO ARTHUR NEGRETE
HVAC-Final 5/28/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 5/28/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 5/28/2026 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 5/28/2026 Approved ARTHUR NEGRETE