4030 S TIVOLI AVE 90066

Certificate Information: 4030 S TIVOLI AVE 90066

Application / Permit
24014-10000-05429
Plan Check / Job No.
B24LA35451
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INTERIOR REMODEL AND 2ND STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING NFPA13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 4/25/2025
Issuing Office
Metro
Current Status
CofO Issued on 2/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 JAD BASMA
Corrections Issued 1/2/2025 JAD BASMA
Quality Review Completed 1/3/2025 KEN GILL
Building Plans Picked Up 1/6/2025 APPLICANT
Plan Check Approved 3/26/2025 JAD BASMA
Issued 4/25/2025 APPLICANT
CofO in Progress 2/3/2026 ANTHONY EGSON
Permit Finaled 2/5/2026 RICHARD STEINBACH
CofO Issued 2/5/2026 RICHARD STEINBACH
Permit Finaled 2/5/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/2/2025 LIAM ODONOVAN
Sewer availability Cleared 1/2/2025 LIAM ODONOVAN
Hydrant and Access approval Cleared 1/6/2025 PATRICK PEREZ
Specific Plan Cleared 2/13/2025 FREDDY GARCIA
Roof/Waste drainage to street Cleared 2/15/2025 LIAM ODONOVAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/6/2025 Conditional Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/11/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 8/29/2025 Corrections Issued WILBER ROSALES
ELECTRICAL-Rough 8/29/2025 Partial Approval WILBER ROSALES
HVAC-Rough 8/29/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved WILBER ROSALES
PLUMBING-Rough 9/4/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 9/29/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 9/29/2025 Approved WILBER ROSALES
Green Building Rough 9/29/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 9/29/2025 Partial Approval WILBER ROSALES
Verify Sprinkler Sign Off 9/29/2025 Approved WILBER ROSALES
Insulation 10/7/2025 Corrections Issued WILBER ROSALES
Drywall Nailing 10/15/2025 Approved WILBER ROSALES
Insulation 10/15/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 10/16/2025 Approved WILBER ROSALES
Shower Pan 10/16/2025 Approved WILBER ROSALES
Sewer 11/3/2025 Approved WILBER ROSALES
Underground Mechanical 11/3/2025 Approved WILBER ROSALES
ELECTRICAL-Final 12/23/2025 Approved WILBER ROSALES
Final 12/23/2025 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 12/23/2025 Approved WILBER ROSALES
Green Building Final 12/23/2025 Corrections Issued WILBER ROSALES
HVAC-Final 12/23/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 12/23/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Not Required WILBER ROSALES
Smoke Detectors 12/23/2025 Approved WILBER ROSALES
Final 12/30/2025 Not Ready for Inspection WILBER ROSALES
Green Building Final 12/30/2025 Not Ready for Inspection WILBER ROSALES
Service/Power Release 1/22/2026 Approved RICHARD STEINBACH
Final 2/2/2026 OK to Issue CofO ANTHONY EGSON
Green Building Final 2/2/2026 Approved ANTHONY EGSON
HVAC-Final 2/2/2026 Approved ANTHONY EGSON
PLUMBING-Final 2/2/2026 Approved ANTHONY EGSON