3721 N LOWELL AVE 90032
Certificate Information: 3721 N LOWELL AVE 90032
- Application / Permit
- 24014-10000-05424
- Plan Check / Job No.
- B24LA35426
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SFD ADDITION PER WFPP
- Permit Issued
- Issued on 12/24/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 12/10/2024 | JOSE VELAZQUEZ |
| Plan Check Approved | 12/24/2024 | EDWIN MARTINEZ |
| Issued | 12/24/2024 | APPLICANT |
| CofO in Progress | 3/18/2025 | LILIANA PORTILLO |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
| CofO Issued | 3/20/2025 | DEROLD HAUFF |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2024 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 12/16/2024 | MICHAEL TEMPLE |
| Roof/Waste drainage to street | Cleared | 12/16/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/28/2025 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Partial Approval | LILIANA PORTILLO |
| Insulation | 1/29/2025 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/7/2025 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/7/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 2/12/2025 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 2/12/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/12/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/27/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Drywall Nailing | 2/27/2025 | Approved | LILIANA PORTILLO |
| Final | 2/27/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 2/27/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 2/27/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/27/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/27/2025 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 2/27/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/17/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/17/2025 | Approved | LILIANA PORTILLO |
| Final | 3/17/2025 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 3/17/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 3/17/2025 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 3/17/2025 | Approved | LILIANA PORTILLO |