14242 W HORTENSE ST 91423
Certificate Information: 14242 W HORTENSE ST 91423
- Application / Permit
- 24014-10000-05413
- Plan Check / Job No.
- B24LA35290
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION AND REMODELING OF (E) SFD.
- Permit Issued
- Issued on 2/14/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | JOE VO |
| Corrections Issued | 12/19/2024 | MICHAEL LOPEZ |
| Quality Review Completed | 12/23/2024 | KEN GILL |
| Building Plans Picked Up | 12/26/2024 | APPLICANT |
| Plan Check Approved | 2/13/2025 | JOE VO |
| Issued | 2/14/2025 | APPLICANT |
| CofO in Progress | 1/27/2026 | MISAEL ESPARZA |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
| CofO Issued | 2/12/2026 | RUBEN SALAS |
| Permit Finaled | 2/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/30/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/30/2024 | CARLOS AGUILERA |
| ZI | Cleared | 1/21/2025 | BRENNEN OBETO |
Contact Information
| Contractor | K & K Modern Construction; Lic. No.: 1126272-B | 12838 KLING ST STUDIO CITY, CA 91614 |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/19/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 2/19/2025 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/24/2025 | Partial Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/26/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/19/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/21/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/25/2025 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 6/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 6/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 6/17/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/30/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 6/30/2025 | Not Ready for Inspection | VINCENT HANLEY |
| MERV13>=Rough | 6/30/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 6/30/2025 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/24/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 7/24/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 7/24/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 7/24/2025 | Approved | KEVIN BERBERYAN |
| Wood Frame | 7/24/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 8/14/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/14/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Sewer | 8/14/2025 | Approved | MISAEL ESPARZA |
| Wood Frame | 8/14/2025 | Approved | MISAEL ESPARZA |
| Insulation | 8/19/2025 | Corrections Issued | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 8/19/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 8/28/2025 | Approved | MISAEL ESPARZA |
| Insulation | 8/28/2025 | Approved | MISAEL ESPARZA |
| Shower Pan | 9/18/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/24/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/9/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 1/9/2026 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 1/9/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/14/2026 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 1/14/2026 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 1/14/2026 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | MISAEL ESPARZA |
| Final | 1/20/2026 | OK to Issue CofO | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/20/2026 | Approved | MISAEL ESPARZA |
| Green Building Final | 1/20/2026 | Approved | MISAEL ESPARZA |
| Green Building Rough | 1/20/2026 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 1/20/2026 | Approved | MISAEL ESPARZA |
| MERV13>=Rough | 1/20/2026 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 1/20/2026 | Approved | MISAEL ESPARZA |