13351-13353 W OTSEGO ST 91423

Certificate Information: 13351-13353 W OTSEGO ST 91423

Application / Permit
24014-10000-05412
Plan Check / Job No.
B24LA35288
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. NFPA13D FIRE SPRINKLERS REQUIRED. NEW ATTACHED SB9 SINGLE FAMILY DWELLING TO (E) DETACHED GARAGE. NEW ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 6/12/2025
Issuing Office
Current Status
CofO Issued on 6/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 KEVIN MORALES
Corrections Issued 12/26/2024 KEVIN MORALES
Quality Review Completed 12/30/2024 EUGENE BARBEAU
Applicant returned to address corrections 3/11/2025 KEVIN MORALES
Plan Check Approved 4/3/2025 KEVIN MORALES
Issued 6/12/2025 APPLICANT
CofO in Progress 5/27/2026 MISAEL ESPARZA
Permit Finaled 6/17/2026 RUBEN SALAS
CofO Issued 6/17/2026 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 2/4/2025 WALTER RAMIREZ
Address approval Cleared 2/5/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/5/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/5/2025 LEE GUILBEAUX
Sewer availability Cleared 2/5/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/5/2025 LEE GUILBEAUX
Senate Bill 9 Cleared 3/3/2025 MATHEW QUAN
ZI Cleared 3/3/2025 MATHEW QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Santos,, Roy Francis; Lic. No.: C87898       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/20/2025 Approved MISAEL ESPARZA
Underground Mechanical 7/11/2025 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 7/17/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/18/2025 Approved MISAEL ESPARZA
Sewer 7/23/2025 Approved CHRISTOPHE COCHRAN
Gas Test 7/31/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/18/2025 Corrections Issued JACK KARGODORIAN
Special/Order Compliance 8/28/2025 Approved MISAEL ESPARZA
Wood Frame 9/3/2025 Not Ready for Inspection MISAEL ESPARZA
Gas Test 9/8/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 9/8/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 9/10/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 9/15/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 9/17/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 9/17/2025 Corrections Issued MISAEL ESPARZA
Wood Frame 9/17/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 9/29/2025 Approved MISAEL ESPARZA
Wood Frame 9/29/2025 Corrections Issued MISAEL ESPARZA
Insulation 10/23/2025 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 10/23/2025 Partial Approval MISAEL ESPARZA
Insulation 11/10/2025 Approved MISAEL ESPARZA
Drywall Nailing 11/21/2025 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 11/21/2025 Approved MISAEL ESPARZA
Drywall Nailing 11/25/2025 Approved MICHAEL CORTEZ
Shower Pan 11/25/2025 Approved MICHAEL CORTEZ
Underground Mechanical 1/29/2026 Partial Approval MISAEL ESPARZA
Service/Power Release 2/2/2026 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 3/20/2026 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 3/20/2026 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 3/26/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 3/26/2026 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/1/2026 Corrections Issued DAVID MATSON
HVAC-Final 4/1/2026 Corrections Issued DAVID MATSON
ELECTRICAL-Final 4/14/2026 Approved MISAEL ESPARZA
HVAC-Final 4/14/2026 Corrections Issued MISAEL ESPARZA
HVAC-Final 4/29/2026 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/8/2026 Approved MISAEL ESPARZA
Final 5/8/2026 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 5/8/2026 Approved MISAEL ESPARZA
Final 5/14/2026 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 5/14/2026 SGSOV Approved GAREN HAYRAPETYAN
Final 5/21/2026 OK to Issue CofO MISAEL ESPARZA