1434 W KELLAM AVE 90026
Certificate Information: 1434 W KELLAM AVE 90026
- Application / Permit
- 24014-10000-05373
- Plan Check / Job No.
- B24LA30688
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] CONVERT (E) GARAGE WITH NEW ADDITION TO ADU PER CA Govt. Code65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 4/16/2025
- Issuing Office
- Current Status
- Issued on 4/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 12/5/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 12/18/2024 | TU HUA |
| Applicant returned to address corrections | 2/12/2025 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 4/10/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 4/16/2025 | MAHNAZ NOURHASHEMI |
| Issued | 4/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2025 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 1/6/2025 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 1/7/2025 | JUSTIN BICOL |
| Grading Pre-Inspection | Cleared | 2/25/2025 | MICHAEL TEMPLE |
| ZI | Cleared | 3/24/2025 | JACQUELINE TORRES |
| HPOZ | Cleared | 4/10/2025 | SUKI GERSHENHORN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sin,, John Paul; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/28/2025 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/2/2025 | Corrections Issued | BRENDAN MORELLI |
| METHANE-Barrier | 5/2/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| METHANE-Subgrade | 5/2/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 5/6/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| METHANE-Barrier | 5/6/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| METHANE-Subgrade | 5/6/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/8/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| METHANE-Barrier | 5/8/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| METHANE-Subgrade | 5/8/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/12/2025 | Approved | HAMIK HARTOUNIAN |
| METHANE-Barrier | 5/12/2025 | Approved | HAMIK HARTOUNIAN |
| METHANE-Subgrade | 5/12/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/3/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 6/3/2025 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Gas Test | 6/5/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/5/2025 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 6/5/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/6/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 6/6/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/9/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 6/9/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/10/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 6/10/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/10/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 6/10/2025 | Approved | HAMIK HARTOUNIAN |
| METHANE-Rough | 6/10/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 6/16/2025 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 6/16/2025 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 6/16/2025 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/17/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/20/2025 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2025 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/24/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/26/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/26/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 6/26/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 6/26/2025 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 6/30/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 6/30/2025 | Approved | ALEX COLIN |
| Special/Order Compliance | 6/30/2025 | Partial Inspection | DEVON JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Approved | HAMIK HARTOUNIAN |
| Sewer | 7/21/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 3/26/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 3/26/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 3/26/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/26/2026 | Approved | HAMIK HARTOUNIAN |