463 N HOBART BLVD 90004
Certificate Information: 463 N HOBART BLVD 90004
- Application / Permit
- 24014-10000-05370
- Plan Check / Job No.
- B24LA34898
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ACCESSORY DWELLING UNIT AND COVERED PORCH ADDITION TO (E) DETACHED GARAGE PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 4/25/2025
- Issuing Office
- Current Status
- Issued on 4/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 1/7/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/11/2025 | GURUNATH NESARAJAH |
| Issued | 4/25/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/25/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/25/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/16/2025 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 9/23/2025 | Corrections Issued | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 9/30/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/3/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/3/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 12/3/2025 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 12/3/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 12/3/2025 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 12/3/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/4/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/4/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 12/4/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 12/4/2025 | Approved | JEFFREY MEAD |
| Insulation | 1/26/2026 | Approved | JEFFREY MEAD |
| Drywall Nailing | 4/9/2026 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 4/9/2026 | Approved | RONNIE MINDANAO |
| Shower Pan | 4/9/2026 | Approved | RONNIE MINDANAO |