8332 S GONZAGA AVE 90045
Certificate Information: 8332 S GONZAGA AVE 90045
- Application / Permit
- 24014-10000-05304
- Plan Check / Job No.
- B24LA34321
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: PARTIAL GARAGE TO BE CONVERTED INTO A.D.U. (266 SQ. FT.) - NEW BEDROOM, BATH & LINEN NEW ADDITION (381 SQ. FT.) - NEW KITCHEN, DINING & LIVING ROOM TOAL ADU SIZE 647 SQ.FT PARTIAL GARAGE TO BE CONVERTED INTO STORAGE/LAUNDRY (99 SQ. FT.) - NEW LAUNDRY
- Permit Issued
- Issued on 3/24/2025
- Issuing Office
- Current Status
- CofO Issued on 10/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/6/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/12/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/23/2025 | LUISANGEL VALENZUELA |
| Issued | 3/24/2025 | APPLICANT |
| CofO in Progress | 10/21/2025 | JESUS PINEDA |
| Permit Finaled | 10/27/2025 | RICHARD STEINBACH |
| CofO Issued | 10/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/4/2025 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 2/19/2025 | CHRISTINA BRACO |
| Specific Plan | Cleared | 2/19/2025 | HAMID GHAEMMAGHAMI |
| ZA Case | Cleared | 2/22/2025 | NATHAN ROMINE |
| Address approval | Cleared | 3/10/2025 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2025 | CHRISTINA BRACO |
| Sewer availability | Cleared | 3/11/2025 | CHRISTINA BRACO |
Contact Information
| Contractor | A P Remodeling Inc; Lic. No.: 1049032-B | , |
| Contractor | Ap Remodeling Inc; Lic. No.: 1049032-B | , |
| Engineer | Dominguez,, Refugio; Lic. No.: NA50820 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/24/2025 | Conditional Approval | JESUS PINEDA |
| PLUMBING-Rough | 5/1/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Sewer | 5/1/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 5/5/2025 | Conditional Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/5/2025 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 5/5/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/30/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 6/30/2025 | Approved | RUBEN RIVAS |
| Wood Frame | 6/30/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 7/2/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 7/2/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/15/2025 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 7/15/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/15/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 7/21/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 7/23/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/5/2025 | Approved | JESUS PINEDA |
| Shower Pan | 8/5/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/9/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 10/9/2025 | Corrections Issued | JESUS PINEDA |
| Final | 10/9/2025 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 10/9/2025 | Approved | JESUS PINEDA |
| Green Building Final | 10/9/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 10/9/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 10/9/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 10/9/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 10/21/2025 | Approved | JESUS PINEDA |
| Final | 10/21/2025 | OK to Issue CofO | JESUS PINEDA |
| Gas Test | 10/21/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 10/21/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 10/21/2025 | Approved | JESUS PINEDA |