8332 S GONZAGA AVE 90045

Certificate Information: 8332 S GONZAGA AVE 90045

Application / Permit
24014-10000-05304
Plan Check / Job No.
B24LA34321
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: PARTIAL GARAGE TO BE CONVERTED INTO A.D.U. (266 SQ. FT.) - NEW BEDROOM, BATH & LINEN NEW ADDITION (381 SQ. FT.) - NEW KITCHEN, DINING & LIVING ROOM TOAL ADU SIZE 647 SQ.FT PARTIAL GARAGE TO BE CONVERTED INTO STORAGE/LAUNDRY (99 SQ. FT.) - NEW LAUNDRY
Permit Issued
Issued on 3/24/2025
Issuing Office
Current Status
CofO Issued on 10/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2024 APPLICANT
Assigned to Plan Check Engineer 12/6/2024 LUISANGEL VALENZUELA
Corrections Issued 12/6/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/12/2025 LUISANGEL VALENZUELA
Plan Check Approved 3/23/2025 LUISANGEL VALENZUELA
Issued 3/24/2025 APPLICANT
CofO in Progress 10/21/2025 JESUS PINEDA
Permit Finaled 10/27/2025 RICHARD STEINBACH
CofO Issued 10/27/2025 RICHARD STEINBACH
Permit Finaled 10/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 2/4/2025 RIDWAN HARDY
Roof/Waste drainage to street Cleared 2/19/2025 CHRISTINA BRACO
Specific Plan Cleared 2/19/2025 HAMID GHAEMMAGHAMI
ZA Case Cleared 2/22/2025 NATHAN ROMINE
Address approval Cleared 3/10/2025 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 3/11/2025 CHRISTINA BRACO
Sewer availability Cleared 3/11/2025 CHRISTINA BRACO

Contact Information

Contractor A P Remodeling Inc; Lic. No.: 1049032-B       ,
Contractor Ap Remodeling Inc; Lic. No.: 1049032-B       ,
Engineer Dominguez,, Refugio; Lic. No.: NA50820       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/24/2025 Conditional Approval JESUS PINEDA
PLUMBING-Rough 5/1/2025 Corrections Issued TEMISTOCLES CAAL
Sewer 5/1/2025 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 5/5/2025 Conditional Approval JESUS RODRIGUEZ
PLUMBING-Rough 5/5/2025 Partial Approval JESUS RODRIGUEZ
Underground Mechanical 5/5/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 6/30/2025 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 6/30/2025 Approved RUBEN RIVAS
Wood Frame 6/30/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 7/2/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 7/2/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/15/2025 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Approved JESUS RODRIGUEZ
Green Building Rough 7/15/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/15/2025 Approved JESUS RODRIGUEZ
Insulation 7/21/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 7/23/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 8/5/2025 Approved JESUS PINEDA
Shower Pan 8/5/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/9/2025 Approved JESUS PINEDA
ELECTRICAL-Final 10/9/2025 Corrections Issued JESUS PINEDA
Final 10/9/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 10/9/2025 Approved JESUS PINEDA
Green Building Final 10/9/2025 Approved JESUS PINEDA
HVAC-Final 10/9/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 10/9/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 10/9/2025 Approved JESUS PINEDA
ELECTRICAL-Final 10/21/2025 Approved JESUS PINEDA
Final 10/21/2025 OK to Issue CofO JESUS PINEDA
Gas Test 10/21/2025 Approved JESUS PINEDA
HVAC-Final 10/21/2025 Approved JESUS PINEDA
PLUMBING-Final 10/21/2025 Approved JESUS PINEDA