17739 W VICTORY BLVD 91335

Certificate Information: 17739 W VICTORY BLVD 91335

Application / Permit
24014-10000-05294
Plan Check / Job No.
B24LA34242
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan CONVERSION OF (E) DETACHED GARAGE TO ADU WITH ADDITION PER GCS 66323(A)(2)
Permit Issued
Issued on 4/12/2025
Issuing Office
Current Status
CofO Issued on 10/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2024 APPLICANT
Assigned to Plan Check Engineer 12/6/2024 MINA HABILI
Corrections Issued 12/7/2024 MINA HABILI
Applicant returned to address corrections 2/6/2025 MINA HABILI
Plan Check Approved 2/12/2025 MINA HABILI
Issued 4/12/2025 APPLICANT
CofO in Progress 10/9/2025 JUAN ALVARADO
Permit Finaled 10/23/2025 JOHN JANSON
CofO Issued 10/23/2025 JOHN JANSON
Permit Finaled 10/23/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/17/2024 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 12/17/2024 KEVIN CHUNG
Roof/Waste drainage to street Cleared 12/17/2024 KEVIN CHUNG
Sewer availability Cleared 12/17/2024 KEVIN CHUNG
Construction near power lines Cleared 1/28/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/29/2025 No Access for Inspection JUAN ALVARADO
Underground Mechanical 4/29/2025 No Access for Inspection JUAN ALVARADO
Deputy Drilled-In Anchors 5/7/2025 Partial Approval JUAN ALVARADO
Footing/Foundation/Slab 5/7/2025 Corrections Issued JUAN ALVARADO
Underground Mechanical 5/7/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 6/3/2025 Approved JUAN ALVARADO
Underground Mechanical 6/10/2025 Approved JUAN ALVARADO
ELECTRICAL-Rough 6/25/2025 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Not Ready for Inspection JUAN ALVARADO
HVAC-Rough 6/25/2025 Approved JUAN ALVARADO
PLUMBING-Rough 6/25/2025 Approved JUAN ALVARADO
Wood Frame 6/25/2025 Corrections Issued JUAN ALVARADO
BUILDING-Rough-Frame 7/7/2025 Partial Approval DAVID SCANTLIN
Green Building Rough 7/7/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 7/10/2025 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 7/14/2025 Approved JUAN ALVARADO
Insulation 7/14/2025 Not Ready for Inspection JUAN ALVARADO
Wood Frame 7/14/2025 Approved JUAN ALVARADO
Drywall Nailing 7/16/2025 Not Ready for Inspection JUAN ALVARADO
Insulation 7/16/2025 Approved JUAN ALVARADO
Drywall Nailing 7/22/2025 Approved JUAN ALVARADO
Shower Pan 7/22/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 7/31/2025 Approved JUAN ALVARADO
Shower Pan 8/4/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 9/9/2025 Approved JUAN ALVARADO
Final 9/9/2025 Corrections Issued JUAN ALVARADO
Green Building Final 9/9/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Approved JUAN ALVARADO
Smoke Detectors 9/9/2025 Not Ready for Inspection JUAN ALVARADO
ELECTRICAL-Final 9/30/2025 Approved JUAN ALVARADO
HVAC-Final 9/30/2025 Approved JUAN ALVARADO
PLUMBING-Final 9/30/2025 Approved JUAN ALVARADO
Final 10/2/2025 Partial Approval JUAN ALVARADO
Smoke Detectors 10/2/2025 Approved JUAN ALVARADO
Final 10/9/2025 OK to Issue CofO JUAN ALVARADO