666 E MILWOOD AVE 90291
Certificate Information: 666 E MILWOOD AVE 90291
- Application / Permit
- 24014-10000-05280
- Plan Check / Job No.
- B24LA34132
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 3/24/2025
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | DANIEL YIP |
| Corrections Issued | 12/7/2024 | DANIEL YIP |
| Quality Review Completed | 12/9/2024 | GARO TELMI |
| Applicant returned to address corrections | 1/15/2025 | DANIEL YIP |
| Plan Check Approved | 3/4/2025 | DANIEL YIP |
| Issued | 3/24/2025 | APPLICANT |
| CofO in Progress | 3/12/2026 | RUBEN RIVAS |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
| CofO Issued | 4/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/26/2024 | DAVID URITA |
| ZA Case | Cleared | 12/26/2024 | DAVID URITA |
| Sewer availability | Cleared | 1/9/2025 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2025 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 1/11/2025 | LIAM ODONOVAN |
| Coastal Zone | Cleared | 2/4/2025 | DAVID URITA |
| Specific Plan | Cleared | 2/13/2025 | JOSHUA JONES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Herrera,, Edgar E; Lic. No.: NA67603 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/4/2025 | Partial Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/9/2025 | Partial Approval | JESUS RODRIGUEZ |
| Pre-Inspection | 4/18/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Underground Mechanical | 4/29/2025 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/2/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/2/2025 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 5/2/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/14/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/30/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/13/2025 | Partial Approval | MICHAEL ALLEN |
| Green Building Rough | 6/13/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Interior/Exterior Lathing | 6/23/2025 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/1/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 7/7/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 7/9/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 7/14/2025 | Corrections Issued | JESUS PINEDA |
| Final | 7/14/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 7/14/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 7/18/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 7/18/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/18/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 7/25/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 7/31/2025 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/13/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 8/13/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 10/9/2025 | Approved | RUBEN RIVAS |
| Shower Pan | 10/9/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 10/27/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 10/27/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 11/20/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 12/26/2025 | Partial Inspection | ANTHONY EGSON |
| HVAC-Final | 12/26/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 2/3/2026 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 2/3/2026 | Approved | RUBEN RIVAS |
| HVAC-Final | 2/3/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 2/3/2026 | Corrections Issued | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 2/3/2026 | Approved | RUBEN RIVAS |
| Final | 2/11/2026 | OK to Issue CofO | RUBEN RIVAS |
| PLUMBING-Final | 2/11/2026 | Approved | RUBEN RIVAS |