836 E 90TH ST 90002
Certificate Information: 836 E 90TH ST 90002
- Application / Permit
- 24014-10000-05277
- Plan Check / Job No.
- B24LA34084
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF AN ADDITION TO GARAGE RESULT IN DETACHED ADU @ REAR OF LOT 1,056 SQ. FT. PER ORDINANCE
- Permit Issued
- Issued on 1/14/2025
- Issuing Office
- Current Status
- CofO Issued on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | LUKE GONZALES |
| Corrections Issued | 12/7/2024 | LUKE GONZALES |
| Building Plans Picked Up | 12/16/2024 | APPLICANT |
| Applicant returned to address corrections | 12/31/2024 | CARLOS MONTES |
| Plan Check Approved | 1/6/2025 | ALEXANDER JOO |
| Issued | 1/14/2025 | APPLICANT |
| CofO in Progress | 6/12/2025 | LUIS CASTRO |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
| CofO Issued | 6/17/2025 | DEROLD HAUFF |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2024 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/20/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 12/26/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/24/2025 | Corrections Issued | JOHN QUINTANILLA |
| Pre-Inspection | 1/24/2025 | Partial Inspection | JOHN QUINTANILLA |
| Underground Mechanical | 1/24/2025 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 1/28/2025 | Approved | JOHN QUINTANILLA |
| Sewer | 2/4/2025 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 3/14/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 3/14/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 3/14/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 3/18/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 3/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 3/18/2025 | Corrections Issued | JOHN QUINTANILLA |
| Wood Frame | 3/18/2025 | Partial Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 3/19/2025 | Approved | JOHN QUINTANILLA |
| Wood Frame | 3/19/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 3/25/2025 | Corrections Issued | JOHN QUINTANILLA |
| Insulation | 3/28/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 4/1/2025 | Conditional Approval | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 4/1/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 4/4/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 5/28/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 5/28/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 5/28/2025 | Corrections Issued | JOHN QUINTANILLA |
| Final | 5/28/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 5/28/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 5/28/2025 | Conditional Approval | JOHN QUINTANILLA |
| HVAC-Final | 5/28/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 5/28/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Sewer | 5/28/2025 | Approved | JOHN QUINTANILLA |
| Smoke Detectors | 5/28/2025 | Approved | JOHN QUINTANILLA |
| Final | 6/4/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Green Building Final | 6/4/2025 | No Access for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Final | 6/5/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 6/5/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 6/5/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Pre-Inspection | 6/9/2025 | Partial Inspection | JOHN QUINTANILLA |
| Service/Power Release | 6/9/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Final | 6/11/2025 | Approved | LUIS CASTRO |
| Final | 6/11/2025 | OK to Issue CofO | LUIS CASTRO |