4540 N BALBOA AVE 91316

Certificate Information: 4540 N BALBOA AVE 91316

Application / Permit
24014-10000-05250
Plan Check / Job No.
B24LA33789
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 1/14/2025
Issuing Office
Current Status
Issued on 1/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/27/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 DANIEL YIP
Corrections Issued 12/7/2024 DANIEL YIP
Quality Review Completed 12/10/2024 GARO TELMI
Plan Check Approved 1/10/2025 DANIEL YIP
Issued 1/14/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/13/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 12/17/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/17/2024 EDGAR ALCARAZ
Tract Map conditions Cleared 12/31/2024 DAVID URITA
ZA Case Cleared 12/31/2024 DAVID URITA

Contact Information

Contractor Mesh Construction Inc; Lic. No.: 1112560-B       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/17/2025 Partial Approval SEAN WIRCH
Deputy Drilled-In Anchors 4/18/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/1/2025 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 5/6/2025 Approved JOHN COLEMAN
Deputy Reinf. Concrete 5/9/2025 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 6/20/2025 Conditional Approval ROBERT GOLD
Deputy Steel/Welding 8/11/2025 Conditional Approval THOMAS FINNILA
Deputy Steel/Welding 8/27/2025 Conditional Approval DAVID SCANTLIN
Deputy Steel/Welding 8/29/2025 Conditional Approval ROBERT GOLD
Deputy Wood Construction 9/15/2025 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 9/16/2025 Corrections Issued THOMAS FINNILA
Green Building Rough 9/16/2025 Not Ready for Inspection THOMAS FINNILA
Structural Steel Frame 9/16/2025 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Not Ready for Inspection SEAN WIRCH
Structural Steel Frame 9/26/2025 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 10/29/2025 Partial Inspection THOMAS FINNILA
ELECTRICAL-Rough 11/7/2025 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 11/7/2025 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 11/24/2025 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 11/24/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/8/2025 Approved THOMAS FINNILA
HVAC-Rough 12/8/2025 Approved THOMAS FINNILA
Interior/Exterior Lathing 12/8/2025 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 12/18/2025 Conditional Approval HENRY KIM
Drywall Nailing 12/22/2025 Partial Approval ROBERT GOLD
Green Building Rough 12/22/2025 Not Ready for Inspection ROBERT GOLD
Deputy Reinf. Concrete 12/23/2025 Partial Approval SEAN WIRCH
PLUMBING-Rough 12/30/2025 Approved MORRIS JACKSON
Deputy Drilled-In Anchors 1/2/2026 Conditional Approval MORRIS JACKSON
Deputy Reinf. Concrete 1/7/2026 Conditional Approval THOMAS FINNILA
Deputy Drilled-In Anchors 1/15/2026 Conditional Approval HENRY KIM
Deputy Drilled-In Anchors 1/20/2026 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 1/26/2026 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 2/23/2026 Approved THOMAS FINNILA
Green Building Rough 2/23/2026 Approved THOMAS FINNILA
Insulation 2/25/2026 Approved MORRIS JACKSON
Drywall Nailing 3/9/2026 Approved THOMAS FINNILA