Certificate Information: 2418 S LOUELLA AVE 90291

Application / Permit
24014-10000-05233
Plan Check / Job No.
B24LA33647
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN-REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING. REMOVE PORTION OF DWELLING. ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/5/2025
Issuing Office
Current Status
Issued on 8/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/16/2024 APPLICANT
Assigned to Plan Check Engineer 12/20/2024 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 12/21/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 4/8/2025 ROSENDO MEDINA
Applicant returned to address corrections 6/25/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 7/2/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 7/9/2025 ARAMIK SHAHMIRZAIAN
Issued 8/5/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/22/2025 RYAN CASTRO
Sewer availability Cleared 5/22/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/23/2025 RYAN CASTRO
Specific Plan Cleared 6/23/2025 PEDRO AYALA

Contact Information

Contractor X3 Construction Inc; Lic. No.: 1135918-B       ,
Engineer Xi,, Wang; Lic. No.: C85148 422 FALLINGSTAR      IRVINE, CA 92614

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

PLUMBING-Final 7/9/2026    Time Frame: 11-1
Final 7/9/2026    Time Frame: 11-1
Smoke Detectors 7/9/2026    Time Frame: 11-1
SGSOV-Seismic Gas S/O Valve 7/9/2026    Time Frame: 11-1
Drywall Nailing 7/9/2026    Time Frame: 11-1

Inspection Request History

Pre-Inspection 9/18/2025 Partial Inspection WILBER ROSALES
Excavation/Setback/Form/Re-Bar 11/4/2025 Corrections Issued WILBER ROSALES
Deputy Drilled-In Anchors 11/5/2025 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 11/26/2025 Partial Approval WILBER ROSALES
Footing/Foundation/Slab 11/26/2025 Approved WILBER ROSALES
Sewer 12/10/2025 Partial Approval WILBER ROSALES
BUILDING-Rough-Frame 12/29/2025 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 1/14/2026 Not Ready for Inspection ANTHONY EGSON
Wood Frame 1/14/2026 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 1/21/2026 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Approved ANTHONY EGSON
HVAC-Rough 1/21/2026 Approved ANTHONY EGSON
PLUMBING-Rough 1/21/2026 Approved ANTHONY EGSON
BUILDING-Rough-Frame 2/3/2026 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 3/4/2026 Corrections Issued DAKOTA LOW
Interior/Exterior Lathing 3/9/2026 Partial Approval DAKOTA LOW
BUILDING-Rough-Frame 3/12/2026 Approved RUBEN RIVAS
Insulation 3/17/2026 Approved DAKOTA LOW
Drywall Nailing 3/27/2026 Corrections Issued DAKOTA LOW
Shower Pan 4/2/2026 Approved RUBEN RIVAS
ELECTRICAL-Final 6/4/2026 Not Ready for Inspection DAKOTA LOW
ELECTRICAL-Final 6/17/2026 Corrections Issued DAKOTA LOW
ELECTRICAL-Final 6/22/2026 Corrections Issued DAKOTA LOW
ELECTRICAL-Final 6/25/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Final 6/30/2026 Approved RUBEN RIVAS