12021 W STANWOOD DR 90066

Certificate Information: 12021 W STANWOOD DR 90066

Application / Permit
24014-10000-05211
Plan Check / Job No.
B24LA33444
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ADU WITH 2 STORY ADDITION.
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
CofO Issued on 2/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 ARMEN JIVALAGIAN
Corrections Issued 12/10/2024 ARMEN JIVALAGIAN
Quality Review Completed 12/11/2024 PETER KIM
Applicant returned to address corrections 1/10/2025 ARMEN JIVALAGIAN
Applicant returned to address corrections 2/18/2025 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/5/2025 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/21/2025 ARMEN JIVALAGIAN
Plan Check Approved 4/18/2025 ARMEN JIVALAGIAN
Issued 5/15/2025 APPLICANT
CofO in Progress 2/20/2026 RYAN SALAZAR
Permit Finaled 2/24/2026 RICHARD STEINBACH
Permit Finaled 2/24/2026 RICHARD STEINBACH
CofO Issued 2/24/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 12/20/2024 DARIN LAM
Roof/Waste drainage to street Cleared 12/20/2024 DARIN LAM
Construction near power lines Cleared 1/7/2025 RIDWAN HARDY
Construction within easement Cleared 1/7/2025 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/8/2025 DARIN LAM
Sewer availability Cleared 1/8/2025 DARIN LAM
Grading Pre-Inspection Cleared 1/15/2025 ROBERT PINA
Specific Plan Cleared 2/11/2025 PEDRO AYALA
GPI Written Notices Cleared 2/18/2025 ARMEN JIVALAGIAN

Contact Information

Contractor Ibarra General Construction Inc; Lic. No.: 1035668-B       ,
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/4/2025 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 6/17/2025 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Conditional Approval KIRK SANDERS
HVAC-Rough 7/21/2025 Not Ready for Inspection KIRK SANDERS
Special/Order Compliance 7/21/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 8/19/2025 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Corrections Issued KIRK SANDERS
Green Building Rough 8/19/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 8/19/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 8/19/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 9/2/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 9/2/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Conditional Approval KIRK SANDERS
HVAC-Rough 9/2/2025 Approved KIRK SANDERS
PLUMBING-Rough 9/2/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 9/8/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 9/8/2025 Not Ready for Inspection KIRK SANDERS
Green Building Rough 9/8/2025 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 9/16/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 9/16/2025 Approved KIRK SANDERS
Green Building Rough 9/16/2025 Approved KIRK SANDERS
Insulation 9/16/2025 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 9/16/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 9/16/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 9/26/2025 Corrections Issued KIRK SANDERS
Insulation 9/26/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 9/29/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 10/1/2025 Approved KIRK SANDERS
Drywall Nailing 10/1/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 10/1/2025 Conditional Approval KIRK SANDERS
Special/Order Compliance 10/1/2025 Corrections Issued KIRK SANDERS
Shower Pan 10/6/2025 Approved JAYLIN GRAVITTE
Sewer 11/6/2025 Approved KIRK SANDERS
Underground Mechanical 11/6/2025 Partial Approval KIRK SANDERS
Underground Mechanical 11/14/2025 Approved KIRK SANDERS
ELECTRICAL-Final 12/4/2025 Corrections Issued KIRK SANDERS
HVAC-Final 12/4/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 12/4/2025 Approved KIRK SANDERS
Final 2/5/2026 OK to Issue CofO RYAN SALAZAR
Footing/Foundation/Slab 2/5/2026 Approved RYAN SALAZAR
Green Building Final 2/5/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Approved RYAN SALAZAR
Smoke Detectors 2/5/2026 Approved RYAN SALAZAR