1035 N LORD ST 90033

Certificate Information: 1035 N LORD ST 90033

Application / Permit
24014-10000-05207
Plan Check / Job No.
B24LA33400
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 12'-3" X 11'-2" ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER WFPP
Permit Issued
Issued on 3/24/2025
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 11/28/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 12/28/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/19/2025 SEWADA ZADOORAN MILAGARDI
Issued 3/24/2025 APPLICANT
CofO in Progress 11/18/2025 ALIZAH MAYAGOITIA
Permit Finaled 11/18/2025 DEROLD HAUFF
CofO Issued 11/18/2025 DEROLD HAUFF
Permit Finaled 11/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/6/2024 TREVOR QUAN
Sewer availability Cleared 12/6/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/10/2024 TREVOR QUAN
Grading Pre-Inspection Cleared 12/11/2024 LANNY MERRICK
Miscellaneous Cleared 1/6/2025 ALBERT TAM
Miscellaneous Cleared 1/16/2025 ALBERT TAM
Miscellaneous Cleared 1/16/2025 ALBERT TAM

Contact Information

Architect Driscoll,, Christopher; Lic. No.: NA36073       ,
Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/27/2025 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/27/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/4/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/4/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 9/4/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 9/4/2025 Approved ALIZAH MAYAGOITIA
Wood Frame 9/4/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 9/22/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 9/22/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/22/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 9/22/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 9/22/2025 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 9/22/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Wood Frame 9/22/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/16/2025 Approved REGINA MENDEZ
Insulation 10/22/2025 Approved ALIZAH MAYAGOITIA
Drywall Nailing 10/28/2025 Approved GEM DE OCAMPO
Final 11/12/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 11/12/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Final 11/12/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 11/12/2025 Approved ALIZAH MAYAGOITIA
Final 11/17/2025 Conditional Approval ALIZAH MAYAGOITIA
Final 11/18/2025 OK to Issue CofO ALIZAH MAYAGOITIA