11785 N AVENIDA DEL SOL 91326

Certificate Information: 11785 N AVENIDA DEL SOL 91326

Application / Permit
24014-10000-05180
Plan Check / Job No.
B24LA33088
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 STORY 21'-9" X 16'-1" ADDITION OF BEDROOM/ BATHROOM FOR EXISTING SINGLE FAMILY DWELLING, PER ENGR DESIGN
Permit Issued
Issued on 1/15/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 11/25/2024 ADAM HEGAZI
Corrections Issued 11/26/2024 ADAM HEGAZI
Building Plans Picked Up 12/2/2024 APPLICANT
Applicant returned to address corrections 12/13/2024 KELVIN CHUONG
Issued 1/15/2025 APPLICANT
CofO in Progress 11/7/2025 STEVEN BACK
CofO in Progress 11/15/2025 STEVEN BACK
CofO in Progress 11/21/2025 STEVEN BACK
Permit Finaled 12/13/2025 MICHAEL PELHAM
CofO Issued 12/13/2025 MICHAEL PELHAM
Permit Finaled 12/13/2025 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/23/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/23/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/23/2024 LEE GUILBEAUX

Contact Information

Contractor Mayco Construction Inc; Lic. No.: 1052656-B 18700 LUDLOW ST      NORTHRIDGE, CA 91326
Engineer Rooks,, Bret; Lic. No.: C63445 174 LOMA BONITA      SAN LUIS OBISPO, CA 93401

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/11/2025 Conditional Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 6/23/2025 Corrections Issued STEVEN BACK
PLUMBING-Rough 6/23/2025 Partial Approval STEVEN BACK
Sewer 6/23/2025 Approved STEVEN BACK
BUILDING-Rough-Frame 7/30/2025 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 7/30/2025 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Not Ready for Inspection JEFFREY PARD
Green Building Rough 7/30/2025 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 7/30/2025 Approved JEFFREY PARD
PLUMBING-Rough 7/30/2025 Approved JEFFREY PARD
Deputy Wood Construction 7/31/2025 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 8/4/2025 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Approved JEFFREY PARD
Green Building Rough 8/4/2025 Not Ready for Inspection JEFFREY PARD
Green Building Rough 8/11/2025 Not Ready for Inspection SCOTT SOBEL
Insulation 8/11/2025 Conditional Approval SCOTT SOBEL
Interior/Exterior Lathing 8/11/2025 Partial Approval SCOTT SOBEL
Shower Pan 8/11/2025 Approved SCOTT SOBEL
Drywall Nailing 8/15/2025 Approved JEFFREY PARD
Green Building Rough 8/15/2025 Approved JEFFREY PARD
Interior/Exterior Lathing 8/15/2025 Approved JEFFREY PARD
Shower Pan 8/15/2025 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 10/24/2025 Corrections Issued STEVEN BACK
Final 10/24/2025 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 10/24/2025 Corrections Issued STEVEN BACK
Green Building Final 10/24/2025 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Not Ready STEVEN BACK
Smoke Detectors 10/24/2025 Approved STEVEN BACK
Final 11/3/2025 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 11/3/2025 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Approved STEVEN BACK
Final 11/7/2025 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 11/7/2025 Approved STEVEN BACK
Final 11/17/2025 Corrections Issued STEVEN BACK
Final 11/21/2025 OK to Issue CofO STEVEN BACK