3009 S NORTON AVE 90018

Certificate Information: 3009 S NORTON AVE 90018

Application / Permit
24014-10000-05175
Plan Check / Job No.
B24LA33040
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. PROPOSED REMODEL AND ADDITION TO EXISTING 1 STORY SFD *** BUILDING TO BE EQUIPPED WITH NFPA -13D FIRE SPRINKLERS THROUGHOUT***
Permit Issued
Issued on 2/11/2025
Issuing Office
Current Status
CofO Issued on 2/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 12/5/2024 CRYSTEL MAALOUF
Corrections Issued 12/16/2024 CRYSTEL MAALOUF
Quality Review Completed 12/31/2024 SINA KHOSRAVI
Applicant returned to address corrections 1/27/2025 CRYSTEL MAALOUF
Plan Check Approved 2/3/2025 CRYSTEL MAALOUF
Issued 2/11/2025 APPLICANT
CofO in Progress 2/9/2026 JUSTIN HAWLEY
Permit Finaled 2/10/2026 DEROLD HAUFF
CofO Issued 2/10/2026 DEROLD HAUFF
Permit Finaled 2/10/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/26/2024 ADRIAN SANCHEZ
Sewer availability Cleared 12/26/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/9/2025 ADRIAN SANCHEZ

Contact Information

Architect Ribeiro, De Moura, Ricardo Jorge; Lic. No.: C38075 5236 YARMOUTH AVE #113      ENCINO, CA 91316
Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2025 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/24/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Approval LUIS CASTRO
Deputy Drilled-In Anchors 4/3/2025 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Partial Approval RONNIE MINDANAO
PLUMBING-Rough 4/7/2025 Not Ready for Inspection ARTHUR NEGRETE
Pre-Inspection 4/7/2025 Partial Approval ARTHUR NEGRETE
Rough-Elec/Plmb/HVAC 4/30/2025 Corrections Issued JOSE MACIAS
PLUMBING-Rough 5/2/2025 Approved JOSE MACIAS
BUILDING-Rough-Frame 5/5/2025 Approved WILLIAM SIERRA
ELECTRICAL-Rough 5/5/2025 Approved WILLIAM SIERRA
HVAC-Rough 5/5/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 5/5/2025 Approved WILLIAM SIERRA
Shower Pan 5/5/2025 Approved WILLIAM SIERRA
Insulation 5/15/2025 Approved ENRIQUE MIRELES
Drywall Nailing 5/19/2025 Partial Approval REGINA MENDEZ
Interior/Exterior Lathing 5/19/2025 Approved REGINA MENDEZ
Service/Power Release 6/23/2025 Corrections Issued JUSTIN HAWLEY
ELECTRICAL-Final 10/2/2025 Approved JUSTIN HAWLEY
Final 10/2/2025 Corrections Issued JUSTIN HAWLEY
HVAC-Final 10/2/2025 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Final 10/2/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 10/2/2025 Approved JUSTIN HAWLEY
ELECTRICAL-Final 10/9/2025 Approved JUSTIN HAWLEY
Final 10/9/2025 Corrections Issued JUSTIN HAWLEY
HVAC-Final 10/9/2025 Approved JUSTIN HAWLEY
PLUMBING-Final 10/9/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved JUSTIN HAWLEY
Final 2/9/2026 OK to Issue CofO JUSTIN HAWLEY