1072 W 18TH ST 90731
Certificate Information: 1072 W 18TH ST 90731
- Application / Permit
- 24014-10000-05166
- Plan Check / Job No.
- B24LA32949
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- EPLAN: NEW 26'-2" X 22' IRREG.SHAPED ADDITION TO (E) SFD. INTERIOR REMODEL OF (E) SFD. (1 OF 2)
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Current Status
- CofO Issued on 10/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 12/2/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/22/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/29/2025 | OMAR GARNICA |
| Plan Check Approved | 2/10/2025 | OMAR GARNICA |
| Issued | 3/25/2025 | APPLICANT |
| CofO in Progress | 10/15/2025 | JOSEPH MCGARRY |
| Permit Finaled | 10/22/2025 | ANSON MAGLASANG |
| CofO Issued | 10/22/2025 | ANSON MAGLASANG |
| Permit Finaled | 10/22/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/10/2025 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 1/10/2025 | XOCHITL ARQUIETA |
| Grading Pre-Inspection | Cleared | 1/10/2025 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2025 | XOCHITL ARQUIETA |
| Tenant Habitability Plan | Cleared | 1/29/2025 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Home Technique Inc; Lic. No.: 864810-B | , |
| Engineer | Itani,, Riad Hassan; Lic. No.: C55688 | 2459 W 228TH ST TORRANCE, CA 90501 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/10/2025 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 4/11/2025 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/11/2025 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/28/2025 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/13/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/20/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/20/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/20/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/27/2025 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 5/30/2025 | Approved | JOSEPH MCGARRY |
| Shower Pan | 5/30/2025 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 6/3/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/3/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/9/2025 | Approved | JOSEPH MCGARRY |
| Final | 10/9/2025 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 10/9/2025 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 10/9/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 10/9/2025 | Approved | JOSEPH MCGARRY |
| Final | 10/14/2025 | OK to Issue CofO | JOSEPH MCGARRY |