5903 N TEXHOMA AVE 91316

Certificate Information: 5903 N TEXHOMA AVE 91316

Application / Permit
24014-10000-05145
Plan Check / Job No.
B24LA32628
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ADDITION TO ENLARGE (E) ATTACHED GARAGE AND ADD ATTACHED LAUNDRY ROOM. WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 12/19/2024
Issuing Office
Current Status
CofO Issued on 5/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2024 APPLICANT
Assigned to Plan Check Engineer 11/22/2024 OMAR GARNICA
Corrections Issued 11/23/2024 OMAR GARNICA
Plan Check Approved 12/18/2024 OMAR GARNICA
Issued 12/19/2024 APPLICANT
CofO in Progress 5/5/2025 MORRIS JACKSON
Permit Finaled 5/5/2025 JOHN JANSON
CofO Issued 5/5/2025 JOHN JANSON
Permit Finaled 5/5/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/6/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/6/2024 CARLOS AGUILERA

Contact Information

Contractor Ec1 Builders Inc; Lic. No.: 1075811-B       ,
Engineer Habibi,, Shayaan; Lic. No.: C94225 10535 WILSHIRE BLVD APT 1602      LOS ANGELES, CA 90024

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/24/2025 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 1/27/2025 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 1/30/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 2/24/2025 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 3/6/2025 Corrections Issued MORRIS JACKSON
Interior/Exterior Lathing 3/6/2025 Approved MORRIS JACKSON
Deputy Steel/Welding 3/21/2025 Conditional Approval MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV Not Ready MORRIS JACKSON
BUILDING-Rough-Frame 4/22/2025 Approved MORRIS JACKSON
Final 4/22/2025 Not Ready for Inspection MORRIS JACKSON
Insulation 4/22/2025 Corrections Issued MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Not Ready MORRIS JACKSON
Smoke Detectors 4/22/2025 Not Ready for Inspection MORRIS JACKSON
Drywall Nailing 4/28/2025 Approved MORRIS JACKSON
Final 4/28/2025 Not Ready for Inspection MORRIS JACKSON
Insulation 4/28/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 4/28/2025 Corrections Issued MORRIS JACKSON
Final 5/1/2025 OK to Issue CofO MORRIS JACKSON
Smoke Detectors 5/1/2025 Approved MORRIS JACKSON