352 W CANYON VISTA DR 90065

Certificate Information: 352 W CANYON VISTA DR 90065

Application / Permit
24014-10000-05141
Plan Check / Job No.
B24LA32599
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (12 SF) ON FIRST FLOOR AND INTERIOR REMODEL TO (E) SFD ON 1ST FLOOR TO DINING AND LIVING ROOM, CREATE (N) POWDER ROOM, RELOCATE LAUNDRY ROOM AND KITCHEN. REPLACE WINDOWS AND DOORS.
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 KAMYAR EMAMI
Corrections Issued 12/2/2024 KAMYAR EMAMI
Applicant returned to address corrections 1/23/2025 ISIS ARGUETA
Applicant returned to address corrections 3/6/2025 ISIS ARGUETA
Plan Check Approved 3/13/2025 KAMYAR EMAMI
Issued 3/25/2025 APPLICANT
CofO in Progress 11/18/2025 ALIZAH MAYAGOITIA
Permit Finaled 11/18/2025 DEROLD HAUFF
CofO Issued 11/18/2025 DEROLD HAUFF
Permit Finaled 11/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 12/17/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/8/2025 CELINA MORENO
Hydrant and Access approval Cleared 1/16/2025 JERRY KAO
Specific Plan Cleared 1/21/2025 ANDREA MAGANA-WITHERS
Grading Pre-Inspection Cleared 1/23/2025 RUSSELL BONVOULOIR

Contact Information

Architect Cooke,, Barrett H; Lic. No.: NA37365       ,
Contractor La Remodeling Co; Lic. No.: 932510-B       ,
Contractor Mr Fix Inc; Lic. No.: 932510-B       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/11/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 4/11/2025 Partial Approval ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 5/7/2025 Corrections Issued ALIZAH MAYAGOITIA
Wood Frame 5/7/2025 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/24/2025 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 6/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Insulation 6/24/2025 Approved ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 6/24/2025 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 6/26/2025 Conditional Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/30/2025 Conditional Approval REGINA MENDEZ
Green Building Rough 6/30/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 6/30/2025 Approved REGINA MENDEZ
Drywall Nailing 7/9/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 11/5/2025 Approved ALIZAH MAYAGOITIA
Final 11/5/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 11/5/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 11/5/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 11/5/2025 Approved ALIZAH MAYAGOITIA
Final 11/18/2025 OK to Issue CofO ALIZAH MAYAGOITIA