14081 W LA RUE ST 91340

Certificate Information: 14081 W LA RUE ST 91340

Application / Permit
24014-10000-05138
Plan Check / Job No.
B24VN21436
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Single-story ground floor addition to (E) SFD
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
CofO Issued on 12/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 GEORGE JOLAKIAN
Corrections Issued 11/21/2024 GEORGE JOLAKIAN
Quality Review Completed 11/21/2024 RODOLFO ARIAS
Plan Check Approved 5/15/2025 GEORGE JOLAKIAN
Issued 5/15/2025 APPLICANT
CofO in Progress 11/13/2025 JENNIFER RABUCHIN
Permit Finaled 12/3/2025 RUBEN SALAS
CofO Issued 12/3/2025 RUBEN SALAS
Permit Finaled 12/3/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/26/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/10/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/10/2024 BIAINA HARITUNIAN

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B       ,
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 5/19/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/29/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 5/29/2025 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 5/29/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/29/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 5/30/2025 Partial Approval JENNIFER RABUCHIN
Deputy Wood Construction 6/2/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 6/2/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/11/2025 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 6/11/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 7/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Rough 7/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 7/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/2/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 7/9/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 7/9/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/9/2025 Approved JENNIFER RABUCHIN
Green Building Rough 7/9/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 7/9/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/9/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 7/18/2025 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 7/18/2025 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 7/18/2025 Not Ready for Inspection JENNIFER RABUCHIN
Underground Mechanical 7/18/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/29/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/29/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 7/29/2025 Approved JENNIFER RABUCHIN
Insulation 7/29/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/29/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 7/31/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 7/31/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 11/7/2025 Approved KEVIN BERBERYAN
Final 11/7/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 11/7/2025 Partial Approval KEVIN BERBERYAN
Green Building Final 11/7/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 11/7/2025 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 11/7/2025 Approved KEVIN BERBERYAN
Final 11/12/2025 Partial Inspection KEVIN BERBERYAN
ELECTRICAL-Final 11/14/2025 Approved JENNIFER RABUCHIN
Final 11/14/2025 OK to Issue CofO JENNIFER RABUCHIN
Footing/Foundation/Slab 11/14/2025 Approved JENNIFER RABUCHIN
HVAC-Final 11/14/2025 Approved JENNIFER RABUCHIN
METHANE-Barrier 11/14/2025 Approved JENNIFER RABUCHIN
METHANE-Subgrade 11/14/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/14/2025 Approved JENNIFER RABUCHIN