1267 S REDONDO BLVD 90019

Certificate Information: 1267 S REDONDO BLVD 90019

Application / Permit
24014-10000-05129
Plan Check / Job No.
B24LA32459
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
194 SQ FT 1 STORY ADDITION TO AN EXISTING 1 STORY HOUSE, RENOVATION OF KITCHEN.
Permit Issued
Issued on 3/10/2025
Issuing Office
West Los Angeles
Current Status
Issued on 3/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/18/2024 APPLICANT
Assigned to Plan Check Engineer 11/21/2024 ADAM HEGAZI
Corrections Issued 11/23/2024 ADAM HEGAZI
Building Plans Picked Up 12/3/2024 APPLICANT
Plan Check Approved 2/10/2025 DANIEL SMILEY
Issued 3/10/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/5/2025 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 2/6/2025 CHRISTINA BRACO

Contact Information

Architect Scrafano,, Elissa F; Lic. No.: C26071 163 N SYCAMORE      LOS ANGELES, CA 90036
Contractor Substrata Inc; Lic. No.: 1050826-B 5800-A HANNUM AVE STE 240   SUITE 240    CULVER CITY, CA 90230
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/21/2025 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 3/24/2025 Approved ARTHUR NEGRETE
METHANE-Barrier 3/24/2025 Approved ARTHUR NEGRETE
METHANE-Subgrade 3/24/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/24/2025 Partial Inspection ALEX COLIN
Underground Mechanical 4/14/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 5/9/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 5/9/2025 Approved ARTHUR NEGRETE
METHANE-Rough 5/9/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 5/16/2025 Approved ARTHUR NEGRETE
Deputy Wood Construction 5/16/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 5/16/2025 Approved ARTHUR NEGRETE
HVAC-Rough 5/16/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 5/16/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 5/22/2025 Partial Approval ALEX COLIN
Insulation 6/17/2025 Approved ARTHUR NEGRETE
Shower Pan 6/17/2025 Approved ARTHUR NEGRETE
Drywall Nailing 6/23/2025 Approved ALEX COLIN
PLUMBING-Final 11/18/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 11/19/2025 Approved ARTHUR NEGRETE
Final 11/19/2025 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 11/19/2025 Approved ARTHUR NEGRETE
Final 11/20/2025 Corrections Issued JEFFREY MEAD
Green Building Final 11/20/2025 Corrections Issued JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 11/20/2025 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 11/20/2025 Approved JEFFREY MEAD