832 W 132ND ST 90247
Certificate Information: 832 W 132ND ST 90247
- Application / Permit
- 24014-10000-05119
- Plan Check / Job No.
- B24LA32378
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *Eplan.* Conversion and 2-story addition to (e) detached garage to become two story accessory dwelling unit per GSC 66323(a)(2).
- Permit Issued
- Issued on 9/15/2025
- Issuing Office
- Current Status
- Issued on 9/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | JAD BASMA |
| Corrections Issued | 1/9/2025 | HUAN LE |
| Quality Review Completed | 1/17/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 6/25/2025 | HUAN LE |
| Applicant returned to address corrections | 8/19/2025 | JAD BASMA |
| Plan Check Approved | 8/20/2025 | JAD BASMA |
| Issued | 9/15/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2025 | FRANK SALAZAR |
| Address approval | Cleared | 5/15/2025 | FRANK SALAZAR |
| Roof/Waste drainage to street | Cleared | 5/15/2025 | FRANK SALAZAR |
| Sewer availability | Cleared | 5/15/2025 | FRANK SALAZAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shun,, Hairay; Lic. No.: C42961 | 9817 MILOANN STREET TEMPLE CITY, CA 91780 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/14/2025 | Conditional Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 10/27/2025 | Corrections Issued | BEN MOLSTAD |
| METHANE-Barrier | 10/27/2025 | Not Ready for Inspection | BEN MOLSTAD |
| METHANE-Subgrade | 10/27/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/4/2026 | Partial Approval | JOSEPH MCGARRY |
| METHANE-Barrier | 2/4/2026 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 2/4/2026 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/4/2026 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 2/4/2026 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/11/2026 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/17/2026 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2026 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/3/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 6/3/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| METHANE-Rough | 6/3/2026 | Approved | ARTHUR NEGRETE |
| Wood Frame | 6/3/2026 | Approved | ARTHUR NEGRETE |