949 S 4TH AVE 90019
Certificate Information: 949 S 4TH AVE 90019
- Application / Permit
- 24014-10000-05090
- Plan Check / Job No.
- B24LA32074
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU PER LAMC 12.22 A.33(c)-(d) W/ ADDITION.
- Permit Issued
- Issued on 12/26/2024
- Issuing Office
- Current Status
- CofO Issued on 6/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2024 | SERGIO MUNIZ |
| Corrections Issued | 11/21/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 12/13/2024 | SERGIO MUNIZ |
| Plan Check Approved | 12/17/2024 | SERGIO MUNIZ |
| Issued | 12/26/2024 | APPLICANT |
| CofO in Progress | 6/23/2025 | JOSE MACIAS |
| Permit Finaled | 6/29/2025 | DEROLD HAUFF |
| CofO Issued | 6/29/2025 | DEROLD HAUFF |
| Permit Finaled | 6/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 12/6/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2024 | TREVOR QUAN |
| HPOZ | Cleared | 12/11/2024 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 12/11/2024 | MICAELA TORRES-GIL |
| Sewer availability | Cleared | 12/11/2024 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/27/2025 | Conditional Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 1/29/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 1/29/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 4/8/2025 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/8/2025 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 4/8/2025 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/16/2025 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 4/16/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Pre-Inspection | 4/22/2025 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/7/2025 | Conditional Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 5/7/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 5/7/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 5/7/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 5/7/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | RAUL BARAJAS |
| Insulation | 5/9/2025 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/9/2025 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 5/9/2025 | Approved | RAUL BARAJAS |
| Drywall Nailing | 5/15/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 5/27/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 6/13/2025 | Approved | JOSE MACIAS |
| HVAC-Final | 6/13/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 6/13/2025 | Approved | JOSE MACIAS |
| Final | 6/18/2025 | OK to Issue CofO | JOSE MACIAS |
| Green Building Final | 6/18/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 6/18/2025 | Approved | JOSE MACIAS |