3442 N GREEN VISTA DR 91436
Certificate Information: 3442 N GREEN VISTA DR 91436
- Application / Permit
- 24014-10000-05038
- Plan Check / Job No.
- B24LA31484
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 6/17/2025
- Issuing Office
- Current Status
- Issued on 6/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2024 | CARLOS MONTES |
| Corrections Issued | 11/17/2024 | CARLOS MONTES |
| Building Plans Picked Up | 11/21/2024 | APPLICANT |
| Applicant returned to address corrections | 6/2/2025 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/5/2025 | EDWIN MARTINEZ |
| Issued | 6/17/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/27/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2024 | EDGAR ALCARAZ |
| Specific Plan | Cleared | 4/22/2025 | JUDE HERNANDEZ |
| Hydrant and Access approval | Cleared | 4/29/2025 | PATRICK PEREZ |
| Grading Pre-Inspection | Cleared | 6/17/2025 | CARLOS MONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mchantaf,, Kamal Beshara; Lic. No.: C51050 | 23315 SARATOGA SPRINGS PL MURRIETA, CA 92562 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2025 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 11/19/2025 | Partial Approval | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 11/25/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 12/1/2025 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/5/2025 | Approved | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 1/7/2026 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2026 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 1/22/2026 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 1/22/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Wood Construction | 1/23/2026 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/2/2026 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/2/2026 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 2/2/2026 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/6/2026 | Approved | THOMAS FINNILA |
| Insulation | 2/6/2026 | Approved | THOMAS FINNILA |
| Drywall Nailing | 2/11/2026 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/11/2026 | Order to Comply Issued | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/25/2026 | Approved | THOMAS FINNILA |
| Green Building Rough | 3/25/2026 | Approved | THOMAS FINNILA |