1361 1/2 E 109TH ST 90059

Certificate Information: 1361 1/2 E 109TH ST 90059

Application / Permit
24014-10000-05019
Plan Check / Job No.
B24LA31340
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: New ADU ( 27.33 ft x 18 ft).
Permit Issued
Issued on 12/26/2024
Issuing Office
Current Status
CofO Issued on 11/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 TSE MING HUANG
Corrections Issued 11/15/2024 TSE MING HUANG
Plan Check Approved 12/26/2024 TSE MING HUANG
Issued 12/26/2024 APPLICANT
CofO in Progress 11/21/2025 JOSEPH MCGARRY
Permit Finaled 11/21/2025 ANSON MAGLASANG
CofO Issued 11/21/2025 ANSON MAGLASANG
Permit Finaled 11/21/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/30/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/2/2024 TREVOR QUAN
Sewer availability Cleared 12/2/2024 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mokri, - Arganeh, Fattaneh; Lic. No.: C52608 30281 GRANDE VISTA AVENUE      LAGUNA NIGUEL, CA 92677

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/7/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 4/30/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 5/6/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 5/6/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 5/8/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 5/8/2025 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 5/9/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 5/9/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 6/18/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 6/18/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Partial Approval ANTHONY EGSON
HVAC-Rough 6/18/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 6/18/2025 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 7/9/2025 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 7/9/2025 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 7/9/2025 Not Ready for Inspection JOHN KLARIN
Green Building Rough 7/9/2025 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 7/9/2025 Approved JOHN KLARIN
Wood Frame 7/9/2025 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 7/23/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 7/23/2025 Corrections Issued ANTHONY EGSON
Green Building Rough 7/23/2025 Not Ready for Inspection ANTHONY EGSON
Insulation 7/23/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 8/1/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/1/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 8/1/2025 Approved ANTHONY EGSON
HVAC-Final 8/1/2025 Approved ANTHONY EGSON
PLUMBING-Rough 8/1/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 8/8/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 8/29/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 8/29/2025 Approved ANTHONY EGSON
Insulation 8/29/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 8/29/2025 Approved ANTHONY EGSON
Final 11/18/2025 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 11/18/2025 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 11/18/2025 SGSOV Not Required JOSEPH MCGARRY
Service/Power Release 11/18/2025 Not Required JOSEPH MCGARRY
Smoke Detectors 11/18/2025 Approved JOSEPH MCGARRY