3873 S WESTSIDE AVE 90008
Certificate Information: 3873 S WESTSIDE AVE 90008
- Application / Permit
- 24014-10000-04976
- Plan Check / Job No.
- B24LA30963
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 500 SQ FT ADDITION TO EXISTING SFD, REMODEL (E) KITCHEN, REMODEL MASTER BATH
- Permit Issued
- Issued on 12/16/2024
- Issuing Office
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 11/13/2024 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 11/18/2024 | APPLICANT |
| Plan Check Approved | 12/16/2024 | JOSE VELAZQUEZ |
| Issued | 12/16/2024 | APPLICANT |
| CofO in Progress | 5/6/2025 | LUIS CASTRO |
| CofO Issued | 5/7/2025 | DEROLD HAUFF |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/30/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2024 | ERIK BEASLEY |
Contact Information
| Contractor | Ene Builders; Lic. No.: 1113906-B | 21434 WYANDOTTE STREET CANOGA PARK, CA 91303 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/23/2024 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 12/23/2024 | Not Ready for Inspection | LUIS CASTRO |
| Footing/Foundation/Slab | 12/23/2024 | Approved | LUIS CASTRO |
| Green Building Rough | 12/23/2024 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 12/23/2024 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 12/23/2024 | Not Ready for Inspection | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/10/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 1/10/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 1/10/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 1/10/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 1/14/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 1/14/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 1/14/2025 | Partial Approval | LUIS CASTRO |
| Shower Pan | 1/14/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 1/17/2025 | Partial Approval | ALEX COLIN |
| Interior/Exterior Lathing | 1/17/2025 | Partial Approval | ALEX COLIN |
| Pre-Inspection | 1/30/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Not Ready for Inspection | LUIS CASTRO |
| Deputy Wood Construction | 2/4/2025 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 2/12/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 2/12/2025 | Partial Approval | LUIS CASTRO |
| Wood Frame | 2/12/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 2/13/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 2/18/2025 | Partial Approval | LUIS CASTRO |
| Insulation | 2/20/2025 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 2/24/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/10/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Final | 4/10/2025 | Corrections Issued | LUIS CASTRO |
| Final | 4/10/2025 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Final | 4/10/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 4/10/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 4/10/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/10/2025 | Corrections Issued | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 4/10/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/30/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 4/30/2025 | Approved | LUIS CASTRO |
| Final | 4/30/2025 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 4/30/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/30/2025 | Approved | LUIS CASTRO |