7366 W 83RD ST 90045
Certificate Information: 7366 W 83RD ST 90045
- Application / Permit
- 24014-10000-04975
- Plan Check / Job No.
- B24LA30956
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION TO (E) SFD
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Current Status
- CofO Issued on 5/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2024 | GURUNATH NESARAJAH |
| Corrections Issued | 11/14/2024 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/5/2024 | GURUNATH NESARAJAH |
| Issued | 12/6/2024 | APPLICANT |
| CofO in Progress | 5/14/2025 | JESUS PINEDA |
| Permit Finaled | 5/16/2025 | RICHARD STEINBACH |
| CofO Issued | 5/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/16/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 11/18/2024 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2024 | LIAM ODONOVAN |
| Specific Plan | Cleared | 11/21/2024 | RICHARD WOO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bayani-Rad,, Padra; Lic. No.: NA86320 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/23/2025 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 1/28/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/28/2025 | Partial Approval | TEMISTOCLES CAAL |
| Sewer | 1/28/2025 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 1/29/2025 | Conditional Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/28/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 2/28/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Rough | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/10/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 3/10/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 3/10/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/10/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 3/11/2025 | Approved | JESUS PINEDA |
| Insulation | 3/11/2025 | Approved | JESUS PINEDA |
| Final | 5/12/2025 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 5/12/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 5/12/2025 | Approved | JESUS PINEDA |