7366 W 83RD ST 90045

Certificate Information: 7366 W 83RD ST 90045

Application / Permit
24014-10000-04975
Plan Check / Job No.
B24LA30956
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ADDITION TO (E) SFD
Permit Issued
Issued on 12/6/2024
Issuing Office
Current Status
CofO Issued on 5/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2024 APPLICANT
Assigned to Plan Check Engineer 11/13/2024 GURUNATH NESARAJAH
Corrections Issued 11/14/2024 GURUNATH NESARAJAH
Plan Check Approved 12/5/2024 GURUNATH NESARAJAH
Issued 12/6/2024 APPLICANT
CofO in Progress 5/14/2025 JESUS PINEDA
Permit Finaled 5/16/2025 RICHARD STEINBACH
CofO Issued 5/16/2025 RICHARD STEINBACH
Permit Finaled 5/16/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/16/2024 LIAM ODONOVAN
Grading Pre-Inspection Cleared 11/18/2024 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 11/21/2024 LIAM ODONOVAN
Specific Plan Cleared 11/21/2024 RICHARD WOO

Contact Information

Contractor Owner-Builder       ,
Engineer Bayani-Rad,, Padra; Lic. No.: NA86320       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/23/2025 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 1/28/2025 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 1/28/2025 Partial Approval TEMISTOCLES CAAL
Sewer 1/28/2025 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 1/29/2025 Conditional Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/28/2025 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 2/28/2025 Approved TEMISTOCLES CAAL
Green Building Rough 2/28/2025 Not Ready for Inspection TEMISTOCLES CAAL
HVAC-Rough 2/28/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 2/28/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/10/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Approved JESUS PINEDA
Footing/Foundation/Slab 3/10/2025 Approved JESUS PINEDA
Green Building Rough 3/10/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 3/10/2025 Approved JESUS PINEDA
Drywall Nailing 3/11/2025 Approved JESUS PINEDA
Insulation 3/11/2025 Approved JESUS PINEDA
Final 5/12/2025 OK to Issue CofO JESUS PINEDA
Green Building Final 5/12/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/12/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 5/12/2025 Approved JESUS PINEDA