1501 N STRADELLA ROAD 90077
Certificate Information: 1501 N STRADELLA ROAD 90077
- Application / Permit
- 24014-10000-04953
- Plan Check / Job No.
- B24LA30670
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: REMODEL AND ADD 2-STORY ADDITION TO (E) SFD PER ENGINEER DESIGN
- Permit Issued
- Issued on 3/11/2025
- Issuing Office
- Current Status
- CofO Issued on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | KHUONG TRUONG |
| Corrections Issued | 11/25/2024 | KHUONG TRUONG |
| Quality Review Completed | 11/26/2024 | GARO TELMI |
| Applicant returned to address corrections | 1/28/2025 | KHUONG TRUONG |
| Plan Check Approved | 3/4/2025 | KHUONG TRUONG |
| Issued | 3/11/2025 | APPLICANT |
| Permit Finaled | 12/23/2025 | RICHARD STEINBACH |
| CofO Issued | 12/23/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/23/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/2/2025 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 1/7/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/7/2025 | HISASHI KOBAYAKAWA |
| ZA Case | Cleared | 1/14/2025 | JAZMIN ROQUE |
| Hydrant and Access approval | Cleared | 3/3/2025 | JOHN CONNEALLY |
Contact Information
| Contractor | Hart Design Build Inc; Lic. No.: 1085998-B | , |
| Engineer | Abedian,, Vanik; Lic. No.: S5323 | 2906 JOLLEY DR BURBANK, CA 91504 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2025 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/11/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 7/11/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/24/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/8/2025 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 8/8/2025 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 8/8/2025 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 8/14/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/14/2025 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 8/14/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 8/14/2025 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 8/15/2025 | No Access for Inspection | CHRISTOPHER WILSON |
| Insulation | 8/21/2025 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 8/27/2025 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | CHRISTOPHER WILSON |
| Final | 12/8/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Final | 12/8/2025 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 12/8/2025 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 12/8/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 12/17/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Smoke Detectors | 12/17/2025 | Approved | CHRISTOPHER WILSON |