3793 W VALLEYBRINK ROAD 90039
Certificate Information: 3793 W VALLEYBRINK ROAD 90039
- Application / Permit
- 24014-10000-04940
- Plan Check / Job No.
- B24LA30446
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: 14'-7" X 5'-2" ADDITTION TO AND CONVERT (E) 324 SF DET GARAGE TO NEW ADU PER LAMC 12..2 A.33 (E) AND(C), ALL WORK PER ENG.
- Permit Issued
- Issued on 2/5/2025
- Issuing Office
- Current Status
- CofO Issued on 7/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/13/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/11/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/12/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 2/3/2025 | PINANK PATEL |
| Issued | 2/5/2025 | APPLICANT |
| CofO in Progress | 7/15/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
| Permit Finaled | 7/20/2025 | DEROLD HAUFF |
| CofO Issued | 7/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/4/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/9/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 1/30/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nishimura,, Kentaro; Lic. No.: NA73821 | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/3/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Deputy Drilled-In Anchors | 3/5/2025 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 3/5/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 3/5/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Underground Mechanical | 3/19/2025 | Partial Approval | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 4/16/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 4/16/2025 | Partial Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 5/8/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 5/8/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| MERV13>=Rough | 5/8/2025 | Approved | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 5/8/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Special/Order Compliance | 5/8/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Rough | 5/20/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 5/20/2025 | Partial Approval | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 5/20/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 5/22/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 5/27/2025 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 6/4/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 6/4/2025 | Approved | REGINA MENDEZ |
| Underground Mechanical | 7/7/2025 | Approved | NICHOLAS LOPEZ |
| Final | 7/14/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 7/14/2025 | Approved | NICHOLAS LOPEZ |
| MERV13>=Final | 7/14/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 7/14/2025 | Approved | NICHOLAS LOPEZ |