4318 N WILKINSON AVE 91604
Certificate Information: 4318 N WILKINSON AVE 91604
- Application / Permit
- 24014-10000-04913
- Plan Check / Job No.
- B24LA30236
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] 1st and 2nd floor addition and major remodel to (E) 1story SFD with new attached 2-car garage. Fire sprinkler NFPA13D
- Permit Issued
- Issued on 9/30/2025
- Issuing Office
- Current Status
- Issued on 9/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2024 | KHEDER ALRAZAA |
| Corrections Issued | 11/14/2024 | KHEDER ALRAZAA |
| Quality Review Completed | 11/15/2024 | GARO TELMI |
| Applicant returned to address corrections | 1/2/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 1/23/2025 | KHEDER ALRAZAA |
| No Progress | 1/31/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 1/31/2025 | KHEDER ALRAZAA |
| No Progress | 9/30/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 9/30/2025 | KHEDER ALRAZAA |
| Issued | 9/30/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/22/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 11/25/2024 | RYAN CASTRO |
| ZI | Cleared | 12/13/2024 | DORIAN AGUILAR |
Contact Information
| Contractor | Concept Renovations Inc; Lic. No.: 1016942-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/15/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 12/22/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 12/23/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/6/2026 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/6/2026 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Steel/Welding | 1/13/2026 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/4/2026 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 5/4/2026 | No Access for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/6/2026 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/6/2026 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/6/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/6/2026 | Approved | JAVIER RAMOS JR |