4783 E TEMPLETON ST 90032
Certificate Information: 4783 E TEMPLETON ST 90032
- Application / Permit
- 24014-10000-04897
- Plan Check / Job No.
- B24LA30159
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. 1-story addition to rear side of (e) single story SFD ; add stair and landing at rear side
- Permit Issued
- Issued on 10/7/2025
- Issuing Office
- Current Status
- Issued on 10/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2024 | REZA HAGHIGHAT |
| Corrections Issued | 11/11/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 4/7/2025 | REZA HAGHIGHAT |
| Plan Check Approved | 7/18/2025 | REZA HAGHIGHAT |
| No Progress | 7/24/2025 | REZA HAGHIGHAT |
| Plan Check Approved | 7/24/2025 | REZA HAGHIGHAT |
| Issued | 10/7/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/14/2024 | MICHAEL TEMPLE |
| Roof/Waste drainage to street | Cleared | 5/1/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/1/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/1/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2025 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/15/2025 | JERRY KAO |
| "D" conditions | Cleared | 5/16/2025 | DAVID URITA |
| "Q" conditions | Cleared | 5/16/2025 | DAVID URITA |
| ZI | Cleared | 5/16/2025 | DAVID URITA |
| Disturb/Remove Protected Trees | Cleared | 7/15/2025 | BRANDON WONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/5/2026 | Partial Approval | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 1/16/2026 | Conditional Approval | GEM DE OCAMPO |
| Excavation/Setback/Form/Re-Bar | 1/20/2026 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/6/2026 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 2/6/2026 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2026 | Partial Approval | LILIANA PORTILLO |
| Insulation | 2/10/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/13/2026 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/13/2026 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/19/2026 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 3/19/2026 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/19/2026 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/27/2026 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 3/27/2026 | Approved | LILIANA PORTILLO |
| Insulation | 4/6/2026 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 4/14/2026 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 4/14/2026 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/30/2026 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 4/30/2026 | Approved | ALIZAH MAYAGOITIA |