6902-6904 W WILLOUGHBY AVE 90038

Certificate Information: 6902-6904 W WILLOUGHBY AVE 90038

Application / Permit
24014-10000-04882
Plan Check / Job No.
B24LA29955
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING (E) DETACHED 2 CAR GARAGE TO TWO DETACHED ADU (2 STORIES) PER STATE LAW 1ST FLOOR = ADU #1 = 718 SF 2ND FLOOR = ADU #2 = 622 SF
Permit Issued
Issued on 1/15/2025
Issuing Office
Current Status
CofO Issued on 3/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2024 APPLICANT
Assigned to Plan Check Engineer 11/7/2024 KHUONG TRUONG
Corrections Issued 11/12/2024 KHUONG TRUONG
Quality Review Completed 11/13/2024 KEN GILL
Building Plans Picked Up 11/14/2024 APPLICANT
Plan Check Approved 12/17/2024 KHUONG TRUONG
Issued 1/15/2025 APPLICANT
CofO in Progress 3/4/2026 CRAIG VAUGHAN
Permit Finaled 3/4/2026 DEROLD HAUFF
CofO Issued 3/4/2026 DEROLD HAUFF
Permit Finaled 3/4/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/10/2024 WALLIE JONG
Construction near power lines Cleared 12/10/2024 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 12/10/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/11/2024 WALLIE JONG
Sewer availability Cleared 12/11/2024 WALLIE JONG
Tenant Habitability Plan Cleared 12/11/2024 RICARDO BOHORQUEZ

Contact Information

Contractor Level Frame Construction Inc; Lic. No.: 1078493-B 5401 WEST ADAMS BLVD      LOS ANGELES, CA 90016
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/24/2025 Partial Inspection BRIAN SULLIVAN
Pre-Inspection 2/12/2025 Partial Inspection CRAIG VAUGHAN
Pre-Inspection 2/19/2025 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/5/2025 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 3/5/2025 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Barrier 3/5/2025 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Subgrade 3/5/2025 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/6/2025 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/6/2025 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 4/2/2025 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 4/2/2025 Partial Approval CRAIG VAUGHAN
METHANE-Barrier 4/2/2025 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Subgrade 4/2/2025 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 4/9/2025 Approved CRAIG VAUGHAN
METHANE-Barrier 4/9/2025 Approved CRAIG VAUGHAN
METHANE-Subgrade 4/9/2025 Approved CRAIG VAUGHAN
Wood Frame 4/22/2025 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Partial Approval CRAIG VAUGHAN
HVAC-Rough 5/5/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 5/13/2025 Approved CRAIG VAUGHAN
Deputy Wood Construction 5/28/2025 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/4/2025 Corrections Issued CRAIG VAUGHAN
Green Building Rough 6/4/2025 Approved CRAIG VAUGHAN
METHANE-Rough 6/4/2025 Approved CRAIG VAUGHAN
Wood Frame 6/4/2025 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 6/11/2025 No Access for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 6/11/2025 No Access for Inspection CRAIG VAUGHAN
HVAC-Rough 6/11/2025 No Access for Inspection CRAIG VAUGHAN
Wood Frame 6/11/2025 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 6/13/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 6/13/2025 Approved CRAIG VAUGHAN
HVAC-Rough 6/13/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 6/24/2025 Corrections Issued BRIAN SULLIVAN
Wood Frame 6/24/2025 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 7/1/2025 Approved ROY SPAULDING
Insulation 7/1/2025 Approved ROY SPAULDING
Drywall Nailing 7/9/2025 Approved ROY SPAULDING
Shower Pan 7/10/2025 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 7/24/2025 Partial Approval CRAIG VAUGHAN
Service/Power Release 10/10/2025 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 10/15/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 10/15/2025 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 10/16/2025 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 10/17/2025 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 10/17/2025 Approved CRAIG VAUGHAN
Final 10/22/2025 Corrections Issued CRAIG VAUGHAN
Green Building Final 10/22/2025 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/22/2025 Approved CRAIG VAUGHAN
Final 2/17/2026 Not Ready for Inspection CRAIG VAUGHAN
Final 3/2/2026 OK to Issue CofO CRAIG VAUGHAN