8029 S EL MANOR AVE 90045
Certificate Information: 8029 S EL MANOR AVE 90045
- Application / Permit
- 24014-10000-04870
- Plan Check / Job No.
- B24LA29858
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: New attached trellis and deck at rear of (E) S.F.D. Enlarge existing porch at front of (E) S.F.D. Convert portion of (E) garage to habitable space and remodel throughout (E) S.F.D.
- Permit Issued
- Issued on 1/23/2025
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2024 | CAROLEAN BASMA |
| Corrections Issued | 11/12/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 1/8/2025 | DAVID CASTILLO |
| Plan Check Approved | 1/15/2025 | KAVIAN REFAHI |
| Issued | 1/23/2025 | APPLICANT |
| CofO in Progress | 3/27/2026 | ANTHONY EGSON |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
| CofO Issued | 4/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/3/2024 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 12/3/2024 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2024 | KIMBERLY HERNANDEZ |
| Specific Plan | Cleared | 12/20/2024 | PEDRO AYALA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Architect | Noteware,, Brian Arthur; Lic. No.: NA21514 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 8/4/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 8/7/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 8/7/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 8/7/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 8/14/2025 | Approved | RUBEN RIVAS |
| Deputy Wood Construction | 8/14/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Approved | RUBEN RIVAS |
| Insulation | 9/30/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 10/7/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 10/7/2025 | Partial Approval | RUBEN RIVAS |
| Interior/Exterior Lathing | 11/3/2025 | Approved | JESUS PINEDA |
| Shower Pan | 11/3/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 3/17/2026 | Approved | ANTHONY EGSON |
| Final | 3/17/2026 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/17/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 3/17/2026 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 3/17/2026 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 3/17/2026 | Approved | ANTHONY EGSON |
| Final | 3/23/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 3/23/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/23/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 3/26/2026 | OK to Issue CofO | ANTHONY EGSON |
| PLUMBING-Final | 3/26/2026 | Approved | ANTHONY EGSON |