229 S AVENUE 66 90042

Certificate Information: 229 S AVENUE 66 90042

Application / Permit
24014-10000-04851
Plan Check / Job No.
B24LA29578
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: DETACHED GARAGE CONVERSION TO ADU WITH ADDITION PER GCS 66323(A)(2)
Permit Issued
Issued on 2/16/2025
Issuing Office
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2024 APPLICANT
Assigned to Plan Check Engineer 11/4/2024 JOSE VELAZQUEZ
Corrections Issued 11/5/2024 JOSE VELAZQUEZ
Applicant returned to address corrections 12/16/2024 LUKE GONZALES
Applicant returned to address corrections 2/7/2025 MINA HABILI
Plan Check Approved 2/12/2025 MINA HABILI
Issued 2/16/2025 APPLICANT
CofO in Progress 8/26/2025 DAVID WILLIAMS
Permit Finaled 8/27/2025 DEROLD HAUFF
CofO Issued 8/27/2025 DEROLD HAUFF
Permit Finaled 8/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/14/2024 WALLIE JONG
Construction near power lines Cleared 11/14/2024 ENRIQUE ACOSTA
Roof/Waste drainage to street Cleared 11/14/2024 WALLIE JONG
Miscellaneous Cleared 11/15/2024 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 11/19/2024 WALLIE JONG
Sewer availability Cleared 12/2/2024 WALLIE JONG
HPOZ Cleared 1/29/2025 NATHALY DE LA PAZ
Grading Pre-Inspection Cleared 2/9/2025 JOSE VELAZQUEZ

Contact Information

Contractor Neo Builders And Design Inc; Lic. No.: 1114778-B       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 5306 MULHOLLAND DRIVE      SUMMERVILLE, SC 29485

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/18/2025 Approved DAVID WILLIAMS
Footing/Foundation/Slab 4/22/2025 Not Ready for Inspection DAVID WILLIAMS
Footing/Foundation/Slab 4/25/2025 Approved DAVID WILLIAMS
Underground Mechanical 4/25/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 5/22/2025 Corrections Issued DAVID WILLIAMS
ELECTRICAL-Rough 5/22/2025 Approved DAVID WILLIAMS
Green Building Rough 5/22/2025 Approved DAVID WILLIAMS
HVAC-Rough 5/22/2025 Approved DAVID WILLIAMS
MERV13>=Rough 5/22/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 5/22/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 5/30/2025 Approved REGINA MENDEZ
Shower Pan 5/30/2025 Approved REGINA MENDEZ
Insulation 6/6/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/6/2025 Approved ALIZAH MAYAGOITIA
Insulation 6/9/2025 Approved DAVID WILLIAMS
Drywall Nailing 6/12/2025 Partial Approval REGINA MENDEZ
Drywall Nailing 6/17/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 8/18/2025 Approved DAVID WILLIAMS
ELECTRICAL-Final 8/18/2025 Approved DAVID WILLIAMS
Final 8/18/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 8/18/2025 Conditional Approval DAVID WILLIAMS
HVAC-Final 8/18/2025 Corrections Issued DAVID WILLIAMS
MERV13>=Final 8/18/2025 Approved DAVID WILLIAMS
PLUMBING-Final 8/18/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 8/18/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 8/18/2025 Approved DAVID WILLIAMS
Final 8/26/2025 OK to Issue CofO DAVID WILLIAMS
Green Building Final 8/26/2025 Approved DAVID WILLIAMS