7034 S 7TH AVE 90043
Certificate Information: 7034 S 7TH AVE 90043
- Application / Permit
- 24014-10000-04842
- Plan Check / Job No.
- B24LA29536
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION AND REMODEL TO (E) SFD
- Permit Issued
- Issued on 1/16/2025
- Issuing Office
- Current Status
- Issued on 1/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2024 | JOHNPAUL ISIP |
| Corrections Issued | 11/6/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 12/4/2024 | DAVID CASTILLO |
| Plan Check Approved | 12/10/2024 | DAVID CASTILLO |
| Issued | 1/16/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/2/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/2/2024 | JUSTIN BICOL |
Contact Information
| Architect | Verdugo,, Emilio Amado; Lic. No.: NA33263 | , |
| Contractor | Onyx General Construction Co; Lic. No.: 1095312-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: NA55526 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/22/2025 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 2/19/2025 | Not Ready for Inspection | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 2/27/2025 | Conditional Approval | ANTHONY RAMOS |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 3/4/2025 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Partial Approval | WAYNE REGESTER |
| Wood Frame | 6/24/2025 | Partial Approval | WAYNE REGESTER |
| BUILDING-Rough-Frame | 7/1/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Rough | 7/1/2025 | Partial Approval | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 7/1/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 7/1/2025 | Not Ready for Inspection | WAYNE REGESTER |
| BUILDING-Rough-Frame | 7/8/2025 | Partial Approval | WAYNE REGESTER |
| Interior/Exterior Lathing | 7/8/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 7/22/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 7/22/2025 | Approved | WAYNE REGESTER |
| Insulation | 7/22/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 8/5/2025 | Approved | RONNIE MEDINA |
| Shower Pan | 8/5/2025 | Approved | RONNIE MEDINA |
| Shower Pan | 8/8/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 8/21/2025 | Approved | ANTHONY RAMOS |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | SALVADOR MARTINEZ |
| Final | 1/30/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 1/30/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 1/30/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 2/20/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 2/20/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 2/20/2026 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 5/13/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 5/13/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Final | 5/13/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 5/13/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |