1471-1473 W 35TH PL 90018
Certificate Information: 1471-1473 W 35TH PL 90018
- Application / Permit
- 24014-10000-04839
- Plan Check / Job No.
- B24LA29503
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Major remodel and addition to SFD to create 4-STORY DUPLEX. Sprinklers
- Permit Issued
- Issued on 1/13/2026
- Issuing Office
- Current Status
- Issued on 1/13/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | HERNAN ARREOLA |
| Corrections Issued | 12/31/2024 | HERNAN ARREOLA |
| Quality Review Completed | 1/2/2025 | PETER KIM |
| Applicant returned to address corrections | 11/21/2025 | HERNAN ARREOLA |
| Plan Check Approved | 12/8/2025 | HERNAN ARREOLA |
| Issued | 1/13/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2025 | CELINA MORENO |
| Sewer availability | Cleared | 2/14/2025 | CELINA MORENO |
| Low Impact Development (LID) | Cleared | 2/27/2025 | ERNEST TSE |
| Flood clearance | Cleared | 3/3/2025 | SAMSON WONG |
| Permit | Cleared | 3/13/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 3/13/2025 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 3/27/2025 | SEGAL ISMAEL |
| Hydrant and Access approval | Cleared | 6/13/2025 | LAVEON RIDER |
| Community Plan Implem. Overlay | Cleared | 6/23/2025 | ENRIQUE ACOSTA |
| Community Plan Implem. Overlay | Cleared | 9/30/2025 | MANERI ROMAN |
| Community Plan Implem. Overlay | Cleared | 10/1/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Ace Construction Group Llc; Lic. No.: 1101541-B | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/15/2026 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2026 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 6/11/2026 | Conditional Approval | SABAS ALONSO |
| Underground Mechanical | 6/11/2026 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2026 | Partial Approval | SABAS ALONSO |
| Insulation | 6/17/2026 | Partial Approval | SABAS ALONSO |