3289 S GRANVILLE AVE 90066

Certificate Information: 3289 S GRANVILLE AVE 90066

Application / Permit
24014-10000-04819
Plan Check / Job No.
B24LA29289
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
E-plan. Major remodel and additions to 1-story single family dwelling.
Permit Issued
Issued on 10/6/2025
Issuing Office
Current Status
Issued on 10/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 11/7/2024 HELEN NGUYEN
Corrections Issued 11/12/2024 HELEN NGUYEN
Quality Review Completed 11/18/2024 PETER KIM
Applicant returned to address corrections 3/28/2025 HELEN NGUYEN
Applicant returned to address corrections 6/18/2025 HELEN NGUYEN
Applicant returned to address corrections 8/26/2025 HELEN NGUYEN
Plan Check Approved 9/12/2025 HELEN NGUYEN
Issued 10/6/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/13/2024 HELEN NGUYEN
Sewer availability Cleared 1/31/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 2/3/2025 DARIN LAM
Specific Plan Cleared 2/3/2025 HAMID GHAEMMAGHAMI
Roof/Waste drainage to street Cleared 2/10/2025 DARIN LAM

Contact Information

Contractor Rank-1 Construction Co; Lic. No.: 960933-B       ,
Engineer Grandhi,, Venkata Rohit; Lic. No.: C88709 7823 BOXWOOD CT      HIGHLAND, CA 92346
Engineer Tucker,, Keith D; Lic. No.: GE841 PO BOX 8133      HUNTINGTON BEACH, CA 92615

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/3/2025 Corrections Issued RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 12/2/2025 Corrections Issued DANIEL VERA
Footing/Foundation/Slab 12/8/2025 Corrections Issued KIRK SANDERS
Deputy Drilled-In Anchors 12/15/2025 Conditional Approval DAVID FEILER
Wood Frame 2/6/2026 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 3/11/2026 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/19/2026 Conditional Approval KIRK SANDERS
PLUMBING-Rough 5/19/2026 Partial Approval KIRK SANDERS