1742 S PREUSS ROAD 90035

Certificate Information: 1742 S PREUSS ROAD 90035

Application / Permit
24014-10000-04817
Plan Check / Job No.
B24LA29283
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION, ADDITION OF ATTACHED 2-CAR GARAGE, AND MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING. NFPA 13D
Permit Issued
Issued on 2/10/2025
Issuing Office
Metro
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 VIVIAN LAO
Corrections Issued 11/5/2024 VIVIAN LAO
Quality Review Completed 11/6/2024 KEN GILL
Building Plans Picked Up 11/8/2024 APPLICANT
Applicant returned to address corrections 1/30/2025 VIVIAN LAO
Plan Check Approved 2/5/2025 VIVIAN LAO
Issued 2/10/2025 APPLICANT
CofO in Progress 1/21/2026 WILBER ROSALES
Permit Finaled 1/29/2026 RICHARD STEINBACH
CofO Issued 1/29/2026 RICHARD STEINBACH
Permit Finaled 1/29/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/25/2024 TREVOR QUAN
Low Impact Development (LID) Cleared 12/17/2024 MARCO SANCHEZ
Eng Process Fee Ord 176,300 Cleared 12/18/2024 DAVID LOPEZ
Sewer availability Cleared 12/18/2024 DAVID LOPEZ
Hydrant and Access approval Cleared 12/19/2024 RUEL COLE
Roof/Waste drainage to street Cleared 12/26/2024 DAVID LOPEZ

Contact Information

Contractor Di Nalli Construction; Lic. No.: 942979-B 9055 ALCOTT STREET UNIT 1      LOS ANGELES, CA 90035
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/4/2025 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 3/4/2025 Partial Approval ARAM AVEDISIAN
METHANE-Subgrade 3/4/2025 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 3/4/2025 Partial Approval ARAM AVEDISIAN
METHANE-Subgrade 3/18/2025 Approved EVAN COOPER
Deputy Methane Barrier 3/21/2025 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 3/24/2025 Approved EVAN COOPER
METHANE-Barrier 3/24/2025 Approved EVAN COOPER
METHANE-Rough 3/24/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Partial Approval EVAN COOPER
Deputy Wood Construction 5/22/2025 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval EVAN COOPER
Wood Frame 5/23/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 6/6/2025 Approved EVAN COOPER
HVAC-Rough 6/6/2025 Approved EVAN COOPER
Interior/Exterior Lathing 6/6/2025 Partial Approval EVAN COOPER
PLUMBING-Rough 6/9/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 6/13/2025 Approved EVAN COOPER
Green Building Rough 6/13/2025 Approved EVAN COOPER
METHANE-Rough 6/13/2025 Approved EVAN COOPER
Verify Sprinkler Sign Off 6/13/2025 Approved EVAN COOPER
Insulation 6/18/2025 Approved BOBBY KEY
Drywall Nailing 6/25/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/1/2025 Approved EVAN COOPER
Shower Pan 7/1/2025 Approved EVAN COOPER
ELECTRICAL-Final 11/13/2025 Approved EVAN COOPER
PLUMBING-Final 11/13/2025 Approved EVAN COOPER
HVAC-Final 12/8/2025 Approved EVAN COOPER
Final 1/13/2026 Corrections Issued WILBER ROSALES
Green Building Final 1/13/2026 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved WILBER ROSALES
Smoke Detectors 1/13/2026 Approved WILBER ROSALES
Final 1/15/2026 Corrections Issued ARAM AVEDISIAN
Final 1/20/2026 OK to Issue CofO WILBER ROSALES
Service/Power Release 1/28/2026 Approved DAVID FEILER