631 W 117TH ST 90044

Certificate Information: 631 W 117TH ST 90044

Application / Permit
24014-10000-04815
Plan Check / Job No.
B24LA29276
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel to existing single family dwelling
Permit Issued
Issued on 1/29/2025
Issuing Office
Current Status
CofO Issued on 3/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2024 APPLICANT
Assigned to Plan Check Engineer 11/12/2024 JOHN MESIAS
Corrections Issued 11/13/2024 JOHN MESIAS
Applicant returned to address corrections 12/4/2024 JOSEPH RAFOLS
Plan Check Approved 12/18/2024 SHANGQIN XIE
Issued 1/29/2025 APPLICANT
CofO in Progress 3/6/2026 BEN MOLSTAD
Permit Finaled 3/9/2026 ANSON MAGLASANG
Permit Finaled 3/9/2026 ANSON MAGLASANG
CofO Issued 3/9/2026 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/11/2024 WALLIE JONG
Sewer availability Cleared 12/11/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/17/2024 WALLIE JONG

Contact Information

Contractor Sire Energy Inc; Lic. No.: 1027415-B       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/7/2025 No Access for Inspection BEN MOLSTAD
Footing/Foundation/Slab 3/10/2025 Corrections Issued BEN MOLSTAD
Pre-Inspection 3/10/2025 Corrections Issued BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 3/21/2025 Approved BEN MOLSTAD
Footing/Foundation/Slab 3/21/2025 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Not Ready for Inspection BEN MOLSTAD
Insulation 4/3/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 4/28/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 4/28/2025 Corrections Issued BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Corrections Issued BEN MOLSTAD
HVAC-Rough 4/28/2025 Approved BEN MOLSTAD
MERV13>=Rough 4/28/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 6/4/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 6/4/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 6/4/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 6/6/2025 Approved BEN MOLSTAD
ELECTRICAL-Rough 6/6/2025 Approved BEN MOLSTAD
PLUMBING-Rough 6/6/2025 Approved BEN MOLSTAD
Smoke Detectors 6/6/2025 Not Ready for Inspection BEN MOLSTAD
Insulation 6/10/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 6/10/2025 Partial Approval BEN MOLSTAD
Shower Pan 6/10/2025 Not Ready for Inspection BEN MOLSTAD
Drywall Nailing 6/20/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 6/20/2025 Approved BEN MOLSTAD
Special/Order Compliance 8/26/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 10/3/2025 Approved BEN MOLSTAD
ELECTRICAL-Rough 10/28/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 10/28/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 11/3/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 11/3/2025 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 11/6/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 11/6/2025 Approved BEN MOLSTAD
HVAC-Rough 11/6/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 11/6/2025 Corrections Issued BEN MOLSTAD
Shower Pan 11/6/2025 Approved BEN MOLSTAD
Insulation 11/14/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 11/14/2025 Approved BEN MOLSTAD
Drywall Nailing 11/18/2025 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Not Ready ARTHUR NEGRETE
Final 2/19/2026 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 2/20/2026 Approved BEN MOLSTAD
ELECTRICAL-Final 2/20/2026 Corrections Issued BEN MOLSTAD
Final 2/20/2026 Corrections Issued BEN MOLSTAD
HVAC-Final 2/20/2026 Corrections Issued BEN MOLSTAD
MERV13>=Final 2/20/2026 Approved BEN MOLSTAD
PLUMBING-Final 2/20/2026 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/20/2026 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 2/20/2026 Approved BEN MOLSTAD
ELECTRICAL-Final 2/26/2026 Corrections Issued BEN MOLSTAD
Final 2/26/2026 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Approved BEN MOLSTAD
Final 3/4/2026 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 3/6/2026 Approved BEN MOLSTAD
Final 3/6/2026 OK to Issue CofO BEN MOLSTAD
HVAC-Final 3/6/2026 Approved BEN MOLSTAD
PLUMBING-Final 3/6/2026 Approved BEN MOLSTAD
Service/Power Release 3/6/2026 Approved BEN MOLSTAD