2044 W YOSEMITE DR 90041

Certificate Information: 2044 W YOSEMITE DR 90041

Application / Permit
24014-10000-04799
Plan Check / Job No.
B24LA29053
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and convert (E) detached garage to ADU per state law "COMPLY WITH DEPARTMENT ORDER effective date 09/12/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 1/7/2026
Issuing Office
Current Status
Issued on 1/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/20/2024 APPLICANT
Assigned to Plan Check Engineer 11/26/2024 SHANGQIN XIE
Corrections Issued 11/27/2024 SHANGQIN XIE
Plan Check Approved 1/24/2025 SHANGQIN XIE
Issued 1/7/2026 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/5/2024 ALEXANDER HELFER
Address approval Cleared 12/7/2024 KEVIN AVILA
Eng Process Fee Ord 176,300 Cleared 1/21/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/21/2025 ADRIAN SANCHEZ
Sewer availability Cleared 1/21/2025 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Shower Pan 6/11/2026    Time Frame: 10-12
Gas Test 6/11/2026    Time Frame: 10-12

Inspection Request History

Pre-Inspection 3/19/2026 Approved DANIEL DELACRUZ
Excavation/Setback/Form/Re-Bar 4/1/2026 Approved DANIEL DELACRUZ
PLUMBING-Rough 4/22/2026 Partial Approval DANIEL DELACRUZ
Footing/Foundation/Slab 4/28/2026 Approved DANIEL DELACRUZ
ELECTRICAL-Rough 5/14/2026 Approved DANIEL DELACRUZ
Floor/Roof Diaphrgm/Shear Wall 5/14/2026 Approved DANIEL DELACRUZ
PLUMBING-Rough 5/14/2026 Approved DANIEL DELACRUZ
BUILDING-Rough-Frame 5/19/2026 Partial Approval DANIEL DELACRUZ
HVAC-Rough 5/19/2026 Approved DANIEL DELACRUZ
Interior/Exterior Lathing 5/19/2026 Partial Approval DANIEL DELACRUZ
BUILDING-Rough-Frame 5/20/2026 Approved DANIEL DELACRUZ
Insulation 5/20/2026 Approved DANIEL DELACRUZ
Drywall Nailing 5/27/2026 Approved DANIEL DELACRUZ
Interior/Exterior Lathing 5/27/2026 Approved DANIEL DELACRUZ