6660 E POLLARD ST 90042

Certificate Information: 6660 E POLLARD ST 90042

Application / Permit
24014-10000-04792
Plan Check / Job No.
B24LA28999
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) detached garage with addition to new accessory dwelling unit per LAMC 12.22 A.33(c) and (d) "COMPLY WITH DEPARTMENT ORDER effective date 08/21/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 2/6/2025
Issuing Office
Current Status
Issued on 2/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/26/2024 APPLICANT
Assigned to Plan Check Engineer 10/30/2024 MOHAMMAD ESMAILI
Corrections Issued 10/31/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 1/21/2025 MOHAMMAD ESMAILI
Applicant returned to address corrections 1/28/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 2/2/2025 MOHAMMAD ESMAILI
Issued 2/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/9/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 11/9/2024 JESSICA OPINION
GPI Written Notices Cleared 1/21/2025 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 1/21/2025 MOHAMMAD ESMAILI
Eng Process Fee Ord 176,300 Cleared 1/24/2025 JESSICA OPINION
Sewer availability Cleared 1/24/2025 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/8/2025 Not Ready for Inspection DANIEL DELACRUZ
PLUMBING-Rough 4/10/2025 Partial Approval DANIEL DELACRUZ
Footing/Foundation/Slab 4/16/2025 Partial Approval DANIEL DELACRUZ
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Approved PEDRO SIERRA
BUILDING-Rough-Frame 8/25/2025 Not Ready for Inspection DANIEL DELACRUZ
Green Building Rough 8/25/2025 Approved DANIEL DELACRUZ
PLUMBING-Rough 8/25/2025 Partial Approval DANIEL DELACRUZ
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Approved DANIEL DELACRUZ
PLUMBING-Rough 9/3/2025 Approved DANIEL DELACRUZ
Special/Order Compliance 9/3/2025 Approved DANIEL DELACRUZ
ELECTRICAL-Rough 12/17/2025 Not Ready for Inspection DANIEL DELACRUZ
BUILDING-Rough-Frame 3/23/2026 Partial Approval DANIEL DELACRUZ
ELECTRICAL-Rough 3/23/2026 Partial Approval DANIEL DELACRUZ
PLUMBING-Rough 3/23/2026 Approved DANIEL DELACRUZ