2143 S GREENFIELD AVE 90025
Certificate Information: 2143 S GREENFIELD AVE 90025
- Application / Permit
- 24014-10000-04777
- Plan Check / Job No.
- B24LA28916
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and major remodel to (E) SFD, fire sprinkler NFPA 13D required
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- CofO Issued on 12/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2024 | SHANGQIN XIE |
| Corrections Issued | 10/30/2024 | SHANGQIN XIE |
| Applicant returned to address corrections | 2/19/2025 | SHANGQIN XIE |
| Plan Check Approved | 3/19/2025 | JOSE VELAZQUEZ |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 12/15/2025 | MICHAEL ALLEN |
| Permit Finaled | 12/16/2025 | RICHARD STEINBACH |
| CofO Issued | 12/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/19/2024 | VASIL MIHALEV |
| Specific Plan | Cleared | 11/21/2024 | RICHARD WOO |
| Specific Plan | Cleared | 11/27/2024 | KYLE WINSTON |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2025 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/20/2025 | JEANIE LAM |
| Sewer availability | Cleared | 2/20/2025 | JEANIE LAM |
| GPI Written Notices | Cleared | 3/19/2025 | JOSE VELAZQUEZ |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: NA21514 | , |
| Contractor | Aggregate Construction Group; Lic. No.: 1034714-B | , |
| Contractor | Aggregate Real Estate Solutions; Lic. No.: 1034714-B | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/30/2025 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 5/1/2025 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 5/16/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/6/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 6/6/2025 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Partial Approval | KIRK SANDERS |
| Insulation | 6/16/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 7/3/2025 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 7/22/2025 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 7/22/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/25/2025 | Conditional Approval | ARAM AVEDISIAN |
| HVAC-Rough | 7/25/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/7/2025 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Corrections Issued | SEAN HAUPT |
| Verify Sprinkler Sign Off | 8/7/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 8/13/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 8/13/2025 | Approved | ARAM AVEDISIAN |
| Wood Frame | 8/13/2025 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 8/29/2025 | Corrections Issued | MICHAEL ALLEN |
| Insulation | 9/2/2025 | Not Ready for Inspection | DANIEL VERA |
| Insulation | 9/3/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/5/2025 | Partial Approval | JAYLIN GRAVITTE |
| Shower Pan | 9/5/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 9/10/2025 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/10/2025 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/25/2025 | Partial Approval | ARAM AVEDISIAN |
| Final | 9/25/2025 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/29/2025 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 11/7/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Approved | MICHAEL ALLEN |
| Special/Order Compliance | 11/7/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Final | 12/3/2025 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/5/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 12/5/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 12/5/2025 | Partial Approval | MICHAEL ALLEN |
| Green Building Final | 12/5/2025 | Approved | MICHAEL ALLEN |
| HVAC-Final | 12/5/2025 | No Access for Inspection | MICHAEL ALLEN |
| Smoke Detectors | 12/5/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 12/8/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 12/8/2025 | Approved | MICHAEL ALLEN |
| Final | 12/10/2025 | OK to Issue CofO | MICHAEL ALLEN |
| HVAC-Final | 12/10/2025 | Approved | MICHAEL ALLEN |