1836 W 50TH ST 90062
Certificate Information: 1836 W 50TH ST 90062
- Application / Permit
- 24014-10000-04763
- Plan Check / Job No.
- B24LA26965
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT AND GROUND FLOOR ADDITION PER LAMC 12.22A.33(c)-(d) NFPA 13D
- Permit Issued
- Issued on 1/21/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | VIVIAN LAO |
| Corrections Issued | 10/24/2024 | VIVIAN LAO |
| Quality Review Completed | 10/29/2024 | KEN GILL |
| Building Plans Picked Up | 10/30/2024 | APPLICANT |
| Applicant returned to address corrections | 11/15/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 12/27/2024 | VIVIAN LAO |
| Plan Check Approved | 1/8/2025 | VIVIAN LAO |
| Issued | 1/21/2025 | APPLICANT |
| CofO in Progress | 9/11/2025 | SABAS ALONSO |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
| CofO Issued | 9/13/2025 | DEROLD HAUFF |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 12/4/2024 | TREVOR QUAN |
| Construction near power lines | Cleared | 12/6/2024 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2024 | CELINA MORENO |
| Sewer availability | Cleared | 12/9/2024 | CELINA MORENO |
Contact Information
| Contractor | Nasser Nima; Lic. No.: 1096564-B | 8057 DARBY PL RESEDA, CA 91335 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/24/2025 | Partial Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 2/10/2025 | Partial Approval | SABAS ALONSO |
| Sewer | 2/18/2025 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 2/18/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 2/20/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/28/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 2/28/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 3/6/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 3/21/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 3/21/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 3/21/2025 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 3/21/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 3/24/2025 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 3/28/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 3/28/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 4/2/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/2/2025 | Partial Approval | SABAS ALONSO |
| Shower Pan | 4/2/2025 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/8/2025 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/14/2025 | Approved | SABAS ALONSO |
| Insulation | 4/14/2025 | Approved | SABAS ALONSO |
| Shower Pan | 4/15/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 4/21/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 4/21/2025 | Corrections Issued | ANTHONY RAMOS |
| Interior/Exterior Lathing | 4/28/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 5/7/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/9/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 7/1/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 7/1/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 7/1/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 7/1/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Final | 7/1/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Service/Power Release | 7/1/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 7/1/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Final | 7/28/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/28/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 7/28/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 7/28/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 7/28/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 8/11/2025 | Approved | SABAS ALONSO |
| Final | 8/11/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 8/11/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | SABAS ALONSO |
| ELECTRICAL-Final | 8/13/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 8/13/2025 | Approved | SABAS ALONSO |
| Final | 8/15/2025 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 8/15/2025 | Approved | SABAS ALONSO |
| Final | 9/11/2025 | OK to Issue CofO | SABAS ALONSO |