16639-16641 W BLACKHAWK ST 91344

Certificate Information: 16639-16641 W BLACKHAWK ST 91344

Application / Permit
24014-10000-04735
Plan Check / Job No.
B24LA28510
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GARAGE TO BE CONVERTED TO A JADU PER GCS 65852.2(e)(1)(A) AND BATHROOM ADDITION WITH EXTERIOR ACCESS ONLY. WORK PER WFPP.
Permit Issued
Issued on 11/26/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 NGHI SU
Corrections Issued 10/26/2024 NGHI SU
Building Plans Picked Up 10/30/2024 APPLICANT
Plan Check Approved 11/12/2024 JOHN MESIAS
Issued 11/26/2024 APPLICANT
CofO in Progress 2/25/2026 CHRISTOPHER ROJAS
CofO Issued 3/24/2026 RUBEN SALAS
Permit Finaled 3/24/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/31/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/31/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/31/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/4/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 11/12/2024 WALTER RAMIREZ
Construction within easement Cleared 11/12/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/17/2025 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 1/22/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/27/2025 Conditional Approval KEVIN BERBERYAN
Footing/Foundation/Slab 2/3/2025 No Access for Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 2/11/2025 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 3/10/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 3/10/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 3/10/2025 Approved JAVIER RAMOS JR
HVAC-Rough 3/10/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/10/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/18/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Approved JAVIER RAMOS JR
Green Building Rough 3/18/2025 Approved JAVIER RAMOS JR
Insulation 3/27/2025 Approved JOSE AVILA
Interior/Exterior Lathing 3/27/2025 Approved JOSE AVILA
Drywall Nailing 4/9/2025 Approved NICHOLAS TROWBRIDGE
Shower Pan 4/28/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 5/8/2025 Approved KEVIN BERBERYAN
Sewer 6/2/2025 Approved JAVIER RAMOS JR
Final 7/21/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/21/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/21/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 7/21/2025 Approved CHRISTOPHER ROJAS
Final 7/24/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/24/2025 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 7/24/2025 Approved CHRISTOPHER ROJAS
Final 9/16/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 12/4/2025 Approved MICHEL ABAJAN
Final 12/4/2025 Corrections Issued MICHEL ABAJAN
HVAC-Final 12/4/2025 Approved MICHEL ABAJAN
PLUMBING-Final 12/4/2025 Approved MICHEL ABAJAN
Final 12/26/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 1/7/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/7/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 1/28/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Final 1/28/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 1/28/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Final 2/24/2026 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 2/24/2026 Approved CHRISTOPHER ROJAS