14617 W HUSTON ST 91403

Certificate Information: 14617 W HUSTON ST 91403

Application / Permit
24014-10000-04703
Plan Check / Job No.
B24LA28201
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Remodel of (E) 1-Story SFD & Addition of 2nd Story Enclosure (E) covered patio to living space, convert a portion of (E) SFD area and addtion to attached 2-car garage Per Engineer design ***13D SPRINKLER REQUIRED***
Permit Issued
Issued on 1/16/2025
Issuing Office
Current Status
CofO Issued on 11/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 KHUONG TRUONG
Corrections Issued 10/29/2024 KHUONG TRUONG
Quality Review Completed 11/1/2024 GARO TELMI
Plan Check Approved 1/16/2025 KHUONG TRUONG
Issued 1/16/2025 APPLICANT
CofO in Progress 10/24/2025 JACK KARGODORIAN
CofO Issued 11/25/2025 RUBEN SALAS
Permit Finaled 11/25/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/7/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/12/2024 CARLOS AGUILERA
Sewer availability Cleared 11/12/2024 CARLOS AGUILERA
ZI Cleared 1/15/2025 DORIAN AGUILAR

Contact Information

Contractor Owner-Builder       ,
Engineer Abarquez,, Jose Munoz; Lic. No.: C51994 18 EL CORZO      RANCHO SANTA MARGARITA, CA 92688

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/24/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 2/28/2025 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 2/28/2025 Approved JACK KARGODORIAN
Deputy Drilled-In Anchors 3/7/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/7/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/21/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 3/28/2025 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 4/29/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 5/14/2025 Approved JACK KARGODORIAN
HVAC-Rough 5/14/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 5/14/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 5/23/2025 Partial Approval JENNIFER RABUCHIN
Shower Pan 5/23/2025 Approved JENNIFER RABUCHIN
Insulation 5/30/2025 Conditional Approval LOUIS ESCOTO
Interior/Exterior Lathing 6/6/2025 Partial Approval JACK KARGODORIAN
Drywall Nailing 6/13/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/17/2025 Approved JACK KARGODORIAN
Deputy Drilled-In Anchors 7/25/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 9/9/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 9/9/2025 Not Ready for Inspection JACK KARGODORIAN
Final 9/9/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 9/9/2025 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 9/9/2025 Approved JACK KARGODORIAN
HVAC-Final 9/9/2025 Approved JACK KARGODORIAN
MERV13>=Final 9/9/2025 Approved JACK KARGODORIAN
MERV13>=Rough 9/9/2025 Approved JACK KARGODORIAN
PLUMBING-Final 9/9/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Approved JACK KARGODORIAN
Service/Power Release 9/9/2025 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 9/9/2025 Approved JACK KARGODORIAN
Final 9/11/2025 Not Ready for Inspection JACK KARGODORIAN
Green Building Final 9/11/2025 Not Ready for Inspection JACK KARGODORIAN
Final 10/10/2025 OK to Issue CofO JACK KARGODORIAN
Green Building Final 10/10/2025 Approved JACK KARGODORIAN
Service/Power Release 10/10/2025 Approved JACK KARGODORIAN