10523 W DUNLEER DR 90064

Certificate Information: 10523 W DUNLEER DR 90064

Application / Permit
24014-10000-04693
Plan Check / Job No.
B24LA28094
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Enclose existing deck to create office on 2nd story. Existing 2 story SFD with attached garage
Permit Issued
Issued on 2/25/2025
Issuing Office
Metro
Current Status
CofO Issued on 10/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 MARCELA FRANQUEZ
Corrections Issued 10/26/2024 MARCELA FRANQUEZ
Quality Review Completed 11/1/2024 KEN GILL
Building Plans Picked Up 11/7/2024 APPLICANT
Applicant returned to address corrections 1/13/2025 MARCELA FRANQUEZ
Plan Check Approved 2/6/2025 MARCELA FRANQUEZ
Issued 2/25/2025 APPLICANT
Permit Finaled 10/21/2025 RICHARD STEINBACH
CofO Issued 10/21/2025 RICHARD STEINBACH
Permit Finaled 10/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/16/2025 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 2/5/2025 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 2/6/2025 MARCELA FRANQUEZ

Contact Information

Contractor Rincon Builders Inc; Lic. No.: 988687-B 19528 VENTURA BLVD #183      TARZANA, CA 91356
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/9/2025 Conditional Approval ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 4/14/2025 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 4/14/2025 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 4/28/2025 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 5/8/2025 Conditional Approval ASHLEY THOMPSON
Deputy Steel/Welding 5/8/2025 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 5/12/2025 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 6/16/2025 Corrections Issued ASHLEY THOMPSON
Green Building Rough 6/16/2025 Not Ready for Inspection ASHLEY THOMPSON
Wood Frame 6/16/2025 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 6/25/2025 Partial Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 7/1/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/1/2025 Approved ARAM AVEDISIAN
Green Building Rough 7/1/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/1/2025 Partial Approval ARAM AVEDISIAN
Insulation 7/3/2025 Corrections Issued ASHLEY THOMPSON
Drywall Nailing 7/18/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 9/17/2025 Corrections Issued ASHLEY THOMPSON
Final 9/17/2025 Corrections Issued ASHLEY THOMPSON
Green Building Final 9/17/2025 Approved ASHLEY THOMPSON
HVAC-Final 9/17/2025 Approved ASHLEY THOMPSON
PLUMBING-Final 9/17/2025 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 9/17/2025 Approved ASHLEY THOMPSON
Final 10/16/2025 Conditional Approval ASHLEY THOMPSON