4755 E CATALPA ST 90032
Certificate Information: 4755 E CATALPA ST 90032
- Application / Permit
- 24014-10000-04664
- Plan Check / Job No.
- B24LA27786
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One story 500 SF ADDITIO (E) one-story Single Family Dwelling PER WFPP *** BUILDING TO BE EQUIPPED WIH NFPA-13D FIRE SPRINKLERS THROUGHOUT***
- Permit Issued
- Issued on 2/3/2025
- Issuing Office
- Current Status
- Issued on 2/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2024 | EDWIN MARTINEZ |
| Corrections Issued | 10/28/2024 | EDWIN MARTINEZ |
| Building Plans Picked Up | 10/28/2024 | APPLICANT |
| Plan Check Approved | 2/3/2025 | CRYSTEL MAALOUF |
| Issued | 2/3/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/25/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2024 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/6/2024 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 11/6/2024 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 11/6/2024 | WALLIE JONG |
| "D" conditions | Cleared | 1/30/2025 | JASON CHAN |
| "Q" conditions | Cleared | 1/30/2025 | JASON CHAN |
| ZI | Cleared | 1/30/2025 | JASON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/19/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Pre-Inspection | 3/19/2025 | Partial Inspection | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 3/26/2025 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/26/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/9/2025 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 4/9/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/2/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/2/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 5/2/2025 | Corrections Issued | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 5/2/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/16/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/16/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Conditional Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 5/16/2025 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 5/16/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/20/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 8/20/2025 | Corrections Issued | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 8/20/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/22/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 8/22/2025 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 8/22/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Conditional Approval | BRENDAN MORELLI |
| Wood Frame | 9/25/2025 | Conditional Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 10/24/2025 | Conditional Approval | LILIANA PORTILLO |
| Insulation | 10/24/2025 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/24/2025 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/5/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 11/5/2025 | Approved | LILIANA PORTILLO |
| Insulation | 11/5/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/5/2025 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 11/14/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/14/2025 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/11/2025 | No Access for Inspection | LILIANA PORTILLO |
| Shower Pan | 12/11/2025 | No Access for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/15/2025 | Approved | LILIANA PORTILLO |
| Shower Pan | 12/15/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 3/18/2026 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/18/2026 | Approved | LILIANA PORTILLO |
| Green Building Final | 3/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 3/18/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 3/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |