963-965 N SERRANO AVE 90029

Certificate Information: 963-965 N SERRANO AVE 90029

Application / Permit
24014-10000-04640
Plan Check / Job No.
B24LA27531
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ADDITION AND REMODEL TO (E) 4-UNIT APARTMENT
Permit Issued
Issued on 11/22/2024
Issuing Office
West Los Angeles
Current Status
Issued on 11/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/16/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 DANIEL YIP
Assigned to Zoning Architect 10/17/2024 BENNY WONG
Corrections Issued 10/23/2024 DANIEL YIP
Quality Review Completed 10/24/2024 KEN GILL
Building Plans Picked Up 10/29/2024 APPLICANT
Plan Check Approved 11/20/2024 DANIEL YIP
Issued 11/22/2024 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 10/29/2024 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 11/7/2024 WALLIE JONG
Sewer availability Cleared 11/7/2024 WALLIE JONG
Green Code Cleared 11/17/2024 DANIEL YIP
Zoning Plan Check Cleared 11/18/2024 BENNY WONG

Contact Information

Contractor Everwealth Construction Inc; Lic. No.: 1122780-B 5209 BABCOCK AVE      VALLEY VILLAGE, CA 91607
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/26/2024 Approved TIMOTHY POWELL
Footing/Foundation/Slab 12/9/2024 Not Ready for Inspection LUIS CCAMACHO
Footing/Foundation/Slab 12/13/2024 Partial Inspection ALFREDO LOPEZ
Footing/Foundation/Slab 1/27/2025 Not Ready for Inspection LUIS CCAMACHO
Green Building Rough 1/27/2025 Approved LUIS CCAMACHO
Wood Frame 1/27/2025 Corrections Issued LUIS CCAMACHO
Footing/Foundation/Slab 2/10/2025 Not Ready for Inspection LUIS CCAMACHO
Wood Frame 2/10/2025 Not Ready for Inspection LUIS CCAMACHO
Footing/Foundation/Slab 2/26/2025 Not Ready for Inspection TIMOTHY POWELL
Footing/Foundation/Slab 3/28/2025 Not Ready for Inspection LUIS CCAMACHO
Wood Frame 3/28/2025 Not Ready for Inspection LUIS CCAMACHO
Footing/Foundation/Slab 4/9/2025 No Access for Inspection TIMOTHY POWELL
Wood Frame 4/9/2025 No Access for Inspection TIMOTHY POWELL
Insulation 5/23/2025 Not Ready for Inspection TIMOTHY POWELL
Footing/Foundation/Slab 5/27/2025 Not Ready for Inspection LUIS CCAMACHO
Wood Frame 5/27/2025 Not Ready for Inspection LUIS CCAMACHO
Footing/Foundation/Slab 6/2/2025 Not Ready for Inspection LUIS CCAMACHO
Wood Frame 6/2/2025 Not Ready for Inspection LUIS CCAMACHO
Footing/Foundation/Slab 6/10/2025 Approved TIMOTHY POWELL
Wood Frame 6/10/2025 Corrections Issued TIMOTHY POWELL
Pre-Inspection 8/27/2025 Partial Inspection LUIS CCAMACHO
Wood Frame 1/8/2026 Partial Approval LUIS CCAMACHO
Insulation 2/23/2026 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 2/23/2026 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 3/9/2026 Partial Approval LUIS CCAMACHO