2744 N MANDEVILLE CANYON ROAD 90049
Certificate Information: 2744 N MANDEVILLE CANYON ROAD 90049
- Application / Permit
- 24014-10000-04622
- Plan Check / Job No.
- B24LA27334
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- E-plan. Remodel and addition to single-family house.
- Permit Issued
- Issued on 3/15/2025
- Issuing Office
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 10/23/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/6/2024 | YOUNG KIM |
| Plan Check Approved | 3/14/2025 | ARSALAN SHABESTARI |
| Issued | 3/15/2025 | APPLICANT |
| CofO in Progress | 5/14/2026 | KEVIN SARGSYAN |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
| CofO Issued | 5/19/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/19/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/21/2024 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 11/21/2024 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 11/21/2024 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 11/21/2024 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2024 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 11/26/2024 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 11/26/2024 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 1/7/2025 | LAVEON RIDER |
| Private sewage disp. approval | Cleared | 1/27/2025 | MICHAEL TEMPLE |
| GPI Written Notices | Cleared | 3/14/2025 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 3/14/2025 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Saavedra Construction Inc; Lic. No.: 815140-B | , |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: NA35270 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/3/2025 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 4/3/2025 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/17/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/4/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 8/4/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/4/2025 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 8/4/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/12/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 8/12/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/12/2025 | Approved | KEVIN SARGSYAN |
| Shower Pan | 8/12/2025 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/9/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/9/2025 | Approved | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 9/9/2025 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 9/9/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/9/2025 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/11/2025 | Approved | KEVIN SARGSYAN |
| Insulation | 9/15/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 9/22/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/22/2025 | Approved | KEVIN SARGSYAN |
| Gas Test | 12/3/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 1/30/2026 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 1/30/2026 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 1/30/2026 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 3/2/2026 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 3/2/2026 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 5/12/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| Green Building Final | 5/12/2026 | Approved | KEVIN SARGSYAN |